Two boiler-and-turbine units on the Delaware River south of Philadelphia were supposed to be shut down on May 31, 2025. They are still on call, and on Nov. 20 the Department of Energy gave them another three months.
Read next on Morning Overview: Hidden wear was found inside a New Jersey nuclear reactor during its outage
Units 3 and 4 of Constellation’s Eddystone Generating Station in Pennsylvania are now covered by Order No. 202-26-52, issued under section 202(c) of the Federal Power Act. It is the fourth Eddystone order DOE has issued this year.
Order 202-26-52
According to DOE’s 2026 list of 202(c) orders, the Nov. 20 order is directed to PJM Interconnection, the regional grid operator, working with Constellation Energy Corporation. PJM is to keep Units 3 and 4 available to operate and to use economic dispatch only for the hours needed to meet the emergency. The order takes effect Nov. 21 and runs through Feb. 18, 2027.
The page lists the same two units under three earlier 2026 orders: 202-26-17 on Feb. 23, 202-26-24 on May 21 and 202-26-40 on Aug. 21. Each has covered roughly a quarter of the year.
Built between 1967 and 1970
The American Public Power Association described the plant in 2025 as a six-unit, 820 MW facility on the Delaware River. Units 3 and 4 are each 380 MW subcritical steam units that can burn natural gas or oil, installed between 1967 and 1970, and their planned retirement date was May 31, 2025, the association reported after the first order on May 30, 2025.
That first order said “available generation capacity may fall short of required reserves in an extreme planning scenario,” citing PJM. It was set to expire Aug. 28, 2025, and was extended repeatedly after that. The units have now been held past their retirement date for roughly eighteen months.
The previous order, 202-26-40, ran Aug. 23 through Nov. 20. In the DOE announcement of Aug. 21, Energy Secretary Chris Wright called the energy sources that deliver during peak need the most valuable, and added that coal, natural gas and nuclear “kept the lights and air conditioners on” during recent Mid-Atlantic heat waves, and the release cited DOE’s Resource Adequacy Report, which says power outages could rise about 100-fold by 2030 if the U.S. continues to take reliable power offline.
The August order’s page on DOE’s site records a legal challenge. On Sept. 17, the Natural Resources Defense Council, Citizens for Pennsylvania’s Future, Environmental Defense Fund, Sierra Club and Public Citizen filed a motion to intervene and request for rehearing. On Oct. 22, DOE issued a notice of denial of rehearing by operation of law and provided for further consideration, according to the page.
PJM’s own cost-allocation presentation gives the 2025 chronology: the original order covered June 1 through Aug. 28, 2025, and on Aug. 28 DOE extended it through Nov. 26, 2025. PJM filed on Oct. 6, 2025 to carry its cost methodology over to that extension. The 2026 list then shows the four Eddystone orders dated Feb. 23, May 21, Aug. 21 and Nov. 20. That page covers only orders issued from Jan. 1, 2026 to Dec. 31, 2026, so it does not show what covered the units between Nov. 26, 2025 and Feb. 23, 2026, and nothing read for this article says whether coverage was continuous.
Billing through PJM
Keeping a plant available costs money, and the money is collected from PJM’s customers. A PJM presentation to its Market Settlements Subcommittee, dated Oct. 14, 2025, says the charge for each participant equals its monthly capacity obligation multiplied by a 202(c) charge rate that PJM posts before the monthly bill. Charges are allocated across the grid operator’s territory by each load-serving entity’s share of that obligation, prorated by days and billed with a one-month lag.
The document gives no dollar total for Eddystone, and no cost figure for the Nov. 20 order appears on the DOE page. At that point in 2025, the allocation for an extension that ran through Nov. 26, 2025 was awaiting approval from the Federal Energy Regulatory Commission.
Other plants on the same list
Eddystone is not alone on the DOE list. The 2026 page shows an order for Wagner Generating Station Unit 4 in Maryland dated Nov. 17 and one for the J.H. Campbell plant in Michigan dated Nov. 13, each with its own earlier orders in February, May and August. Beyond single plants, the page also logs PJM system-wide orders dated Jan. 25, Jan. 26, May 18, June 30, July 14, Sept. 1 and Sept. 17, along with orders for Duke Energy, MISO, the Southwest Power Pool, ERCOT and ISO New England. The series numbering runs past 50 for the year, and Eddystone’s is 202-26-52.
Whether the department stops after the February expiry is not stated anywhere in the order record read for this article. Feb. 18, 2027 is the date to watch.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Pieces of a Learjet’s tail landed miles from the Florida crash that killed all nine aboard
- Czech Skyfox jets could become Ukraine’s cheap answer to Shahed attack drones
- A windstorm slammed western Washington, blocking I-5 and knocking out power for thousands
- Tesla’s Cybercab has already crashed 8 times, and the worst one came at highway speed