North America’s power system is stitched together from two big grids that barely talk to each other. In southeastern Wyoming, a planned 106-mile direct-current line is meant to change that, and on Nov. 17 the federal government offered to lend its developer up to $2.8 billion to build it.
The Energy Department says the Wyoming Intertie would double the transfer capacity between the eastern and western halves of the country’s grid. The loan is a conditional commitment, not a closed deal.
A loan offer with conditions attached
The announcement came from DOE’s Office of Energy Dominance Financing. In its Nov. 17 release, the department said the borrower is Grid United and that the commitment of up to $2.8 billion “indicates DOE’s intent to provide a loan,” subject to technical, legal, environmental and financial conditions. Until those are met and definitive documents are signed, no money moves.
The same release says the line will add 1.8 gigawatts of transfer capacity and that “Wyoming Intertie will double existing transfer capacity between the SPP and WECC regions.” SPP is the Southwest Power Pool, which runs the grid across the central United States; WECC is the Western Electricity Coordinating Council, the reliability body for the Western Interconnection.
Energy Secretary Chris Wright said in the release that “projects like Wyoming Intertie will help move more American energy where it’s needed most.” Gregory A. Beard, the director of the financing office, called the project “a prime example of how EDF’s financing can help lower electricity costs.”
A 1.8-gigawatt link between two grids
Trade coverage fills in the engineering. Power Technology reported that the line runs roughly 106 miles through Albany, Carbon and Platte counties, linking Wyoming’s eastern and western electrical interconnections. It uses high-voltage direct-current converter stations that let power cross between grids that are not synchronized with each other, in either direction.
Utility Dive put numbers on the starting point. In its Nov. 18 report, the outlet cited a 2021 DOE statement that existing converter stations allow only 1,320 megawatts to flow between the Western and Eastern interconnections. Adding 1,800 megawatts at one location is the arithmetic behind a claim of doubling at the SPP-WECC seam, though DOE’s release frames the doubling in terms of that interface rather than the continent-wide total.
The loan would run 30 years and cover 80 percent of construction costs, according to Utility Dive, which also reported that Grid United expects permitting to finish in 2029, construction to start in 2030 and operation in 2032 or 2033. Grid United spokesperson Ashley Kang described the site as “a particularly advantageous location for a grid-to-grid connection.”
The $39 billion savings claim
DOE attached a large number to the project. The department estimates it could deliver up to $39 billion in electricity cost savings, benefiting customers across 17 states in the Western Electricity Coordinating Council area over a 30-year life. That figure is DOE’s estimate. The release does not publish the model behind it, and no independent analysis of it has surfaced in the coverage reviewed.
A more modest figure comes with the financing itself: DOE and Grid United say federal borrowing terms would save about $500 million in interest compared with typical private financing, according to Utility Dive and Power Technology.
Price gaps across the seam give the savings argument some footing. Utility Dive cited DOE’s draft 2026 National Transmission Needs Study, which found average price differences along the SPP eastern footprint and Western Interconnection boundary of $18 to $33 per megawatt-hour from 2012 to 2023. A link that lets cheaper power move toward the pricier side narrows such gaps, which is the logic of the savings estimate.
A Wyoming state official was blunter about the pocketbook claim. John Jenks, director of energy market development at the Wyoming Energy Authority, told the outlet in a Nov. 18 local report that the line will not necessarily lower rates, though it could help avoid price spikes, and he called claims of lower monthly bills “a stretch.”
The same report put the project’s total cost at $4 billion and described a route from the Laramie River Station coal plant near Wheatland to the Aeolus substation near Medicine Bow, with roughly 90 percent on state or federal land, according to Beard. Construction Review Online says the project is still in planning, with Grid United working with landowners and Tribal Nations on a preliminary route before filing for regulatory approval, and with county, state and federal approvals still to come.
One of several East-West projects
Wyoming Intertie is not alone. Grid United is developing the North Plains Connector between North Dakota and Montana at 3 gigawatts, the Three Corners Connector between Oklahoma and Colorado at 1.8 gigawatts, and Pecos West between Texas and New Mexico at 1.5 gigawatts, per Utility Dive. A separate Xcel Energy expansion between Colorado and Texas is listed at 490 megawatts, expandable to 2 gigawatts. DOE has agreed to help fund about 6.6 gigawatts of Grid United’s East-West infrastructure, and Utility Dive wrote that the projects together could add about 7 gigawatts of transfer capacity.
The open question is timing. The loan is a statement of intent, the line has permits still to win, and operation is not expected before 2032. Whether the conditions in DOE’s release are satisfied will decide whether the Intertie moves from a federal offer to a working link.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power
- Over 20 trillion gallons of rain fell on the Four Corners states and Nevada in two weeks
- 11 engines built to run well past 200,000 miles
- Two Kentucky residents died when a small plane crashed at Missouri’s Lake of the Ozarks, and the NTSB is investigating