An oil-burning unit built in 1972 on the Patapsco River in Maryland has been told to stay available for the rest of 2026, whether or not its owner or its air permit would otherwise allow it. The order covers Unit 4 at the Wagner Generating Station in Anne Arundel County, and the federal government signed it on Nov. 17 to take effect the next day.
It is the third such order for the same unit this year, and the reasoning has hardly changed since spring: the Mid-Atlantic grid operator used up the unit’s allowed running time in summer heat and says it still needs the plant.
The Energy Department’s order and its conditions
Under Section 202(c) of the Federal Power Act, the Department of Energy can direct a power plant to run during an emergency. The agency’s Nov. 18 announcement says Energy Secretary Chris Wright issued the order to PJM Interconnection, the regional grid operator, in coordination with Talen Energy, which owns Wagner. It runs from Nov. 18 through Dec. 31, 2026.
DOE’s order page for the Wagner series lists the sequence. Order 202-26-25 was issued May 21 and ran to Aug. 19. Order 202-26-25A followed on Aug. 19 and ran to Nov. 17. The latest, 202-26-25B, answers a renewal application PJM filed on Oct. 23.
The announcement gives the rationale in PJM’s own terms. PJM leaned on Wagner Unit 4 during unusually high temperatures earlier this summer, DOE said, which consumed the unit’s remaining operating hours, and PJM has since reaffirmed that it still needs the unit.
An hours cap that keeps running out
The cap is the heart of the matter. Reporting by Power magazine on the first emergency request, in 2025, described how Maryland’s State Implementation Plan limits Wagner 4 to 438 fuel-oil operating hours per calendar year and caps sulfur dioxide emissions at 1,350 pounds per hour. By July 2025, only about 80 oil-burning hours were left, roughly four days of operation, according to PJM.
The unit is rated at 397 megawatts. Talen had planned to retire it by June 1, 2025, citing weak margins and low capacity prices, but PJM found in January 2024 that shutting Wagner 3 and 4 could cause voltage and overload problems in the Baltimore Gas and Electric zone, and a Reliability Must Run arrangement approved by FERC in May 2025 keeps it available through May 2029.
PJM told DOE in 2025 that “if another heatwave like the late June heatwave were to reoccur, there are insufficient run hours remaining because of the Operating Limit on Wagner Unit 4,” according to the Power magazine account. In that article’s telling, PJM had run the unit for 100 hours during the June 23 heat event alone.
The 202(c) orders let PJM run the unit past that cap. The 2025 version did so only during declared emergencies, such as a Maximum Generation Alert, or when modeling showed imminent risk in the BGE zone. The text of Order 202-26-25B sets conditions of its own. Extra hours are allowed when PJM declares or anticipates a Maximum Generation Alert or Transmission Security Emergency, or when dispatch follows the FERC-accepted settlement in Docket ER24-1787. The running is limited to the hours PJM judges necessary to meet the emergency while minimizing ratepayer costs, and it must stop once the emergency is over.
The order does not excuse Talen or PJM from paying emissions fees or buying offsets and allowances, and PJM must notify DOE by the next business day after any dispatch under it, including how far the unit has exceeded its annual limit. DOE also wrote that it disagrees with the D.C. Circuit’s September 2026 Michigan decision while stating that the order is consistent with it.
Wright’s case and what is still unstated
The Secretary framed the order around the national stakes. “Energy shortfalls for 65 million Americans are simply unacceptable,” Wright said in the announcement. He added that previous orders in the mid-Atlantic have helped keep the lights on, and that he expects this one to do the same “in the coming months as well.”
DOE’s own findings in the order cite rising demand and reduced availability of dispatchable generation in the PJM region and a risk of blackouts that could harm public health and safety. The announcement does not break down how much of that winter risk rests on a single 397-megawatt oil unit, and the Power magazine account ties its necessity to voltage support in the Baltimore Gas and Electric zone.
Two things remain open. The first is whether the order will be renewed once it lapses on Dec. 31; every earlier order in the series was followed by another, and the order itself says any renewal must be requested before it expires. The second is cost. Under the 2025 settlement described by Power magazine, Wagner 4 receives $137 per megawatt-day in fixed payments plus performance incentives of $2.5 million a year, and the DOE announcement says nothing about who pays for additional running hours beyond that arrangement.
For now, the record is a federal order in force through Dec. 31, a grid operator that says it needs the unit, and a 438-hour state limit that DOE has set aside. Whether another renewal is filed will show up on the same DOE docket page.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Shaq spent $1.3 million on three Rolls-Royce Phantoms to prove a point to a salesman
- The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power
- Over 20 trillion gallons of rain fell on the Four Corners states and Nevada in two weeks
- 11 engines built to run well past 200,000 miles