Eleven backup power plants in Illinois that burn oil or natural gas were expected to shut down around 2030 or 2031 under the state’s climate law. Two state agencies now propose that the eligible ones keep running at least through May 2033, and the draft plan carrying that idea was opened for public comment on Nov. 16.
The reason, officials say, is demand: Illinois regulators tied the pressure on supply mainly to the build-out of large data centers, and a state study last December flagged possible capacity shortfalls over the next decade.
The draft that would delay closures
The proposal comes from the Illinois Power Agency and the Illinois Environmental Protection Agency, not from the legislature or the Illinois Commerce Commission. On its mitigation plan page, the IPA says the two agencies published the draft Resource Adequacy Mitigation Plan on Nov. 16 for stakeholder feedback, with comments due Jan. 15, 2027, at 5 p.m. Central. After the 60-day window closes, the agencies have 30 days to review comments before filing a final plan with the commission.
The substance is described in a Nov. 19 Alton Telegraph report. It says the draft recommends extending the zero-carbon closure deadlines in the 2021 Climate and Equitable Jobs Act for eligible gas and oil units through at least May 2033, a span the report describes as the 2032-2033 planning year. Coal plants are excluded; regulators cited their higher pollution and environmental justice impacts, and existing coal phaseout schedules are kept.
It is a recommendation. Nothing in the reporting says any unit has been ordered to stay open.
Which plants, and why gas and oil
The Alton report says the eligible gas and oil units often run only during peak seasonal demand hours, and that state modeling suggests keeping them would shield ratepayers from sharp capacity-market price spikes and reduce the need for out-of-state utilities to build new fossil plants to serve Illinois. The study underlying the plan was issued by the IPA, ICC and IEPA together on Dec. 15, 2025 under a section of the Illinois Environmental Protection Act added by the 2021 law.
A separate summary of the Chicago Sun-Times coverage, posted by Let’s Data Science, gives the count: eleven peaker plants had been slated to close in 2030 or 2031, and one report recommends they run until 2033 to help prevent blackouts. Seven coal plants still operate in central and southern Illinois; the goal of closing four by 2030 remains, and three publicly owned coal plants have longer timelines. The same summary says the reports do not advise building new gas plants, leaning instead on nuclear power and plant upgrades.
Named sites in that coverage include the former Fisk coal plant in Pilsen and a Waukegan plant that has operated for more than 90 years.
WBBM Newsradio’s coverage of the reports adds the geography and the other side of the argument. It says the ICC report projects capacity shortages in ComEd’s northern Illinois territory starting in 2030, with a worse situation downstate, and that buying power from other states is not necessarily a workable fix. It also describes the draft as extending the 2030 emission limits for eligible units to 2033, and says some of the affected plants could run only during a limited number of high-risk hours or serve as emergency backup. The Illinois Clean Jobs Coalition, which did not name a speaker, countered in that coverage that “Big Tech data centers are driving this problem.”
The December study that started the process was more general. In the IPA’s announcement of the 2025 study, the agencies said it found resource adequacy challenges in PJM and MISO, the two regional grids serving Illinois, likely to affect the cost and reliability of supply, while concluding the state can meet its electricity-sector climate goals with commercially available technologies. Energy and Environment Economics, known as E3, did the modeling. Specific shortfall figures sit in the study’s executive summary and appendices, which were not reviewed for this article.
A second report and the reactions
The draft arrived alongside a longer-range document. According to the Alton report, ICC staff compiled the Initial Integrated Resource Plan under the Clean and Reliable Grid Affordability Act. It models a 20-year outlook using a reliability benchmark of no more than one day of outage risk every 10 years, and examines transmission expansion, battery storage, nuclear fleet retention and demand-side flexibility. The commission was scheduled to open a docketed review on Nov. 19, with a final decision expected in November 2027. The report says the plan does not predict imminent blackouts.
Officials framed the work around affordability. Jonathan Feipel, the ICC’s executive director, said “Energy affordability and sustained resource adequacy are top priorities at the ICC.” Brian Granahan, the IPA’s director, said the draft plan “places resilience, stability, and energy affordability front and center.”
Reaction split along familiar lines. Mark Denzler, president and CEO of the Illinois Manufacturers’ Association, welcomed the gas and oil reprieve but said it is not enough, noting manufacturing is 14 percent of the state’s economic output and urging policymakers to “maintain all current generation facilities” while investing in new generation and carbon capture. Solar Powers Illinois, a statewide coalition, argued that the grid can already absorb at least 15 gigawatts of additional distributed solar, enough for more than 2.5 million homes, and said “solar and storage are the fastest and most cost-effective forms of energy to build.”
What happens next is a public record: comments through Jan. 15, a final plan filed with the ICC, and then the commission’s own litigated review. Lawmakers are expected to take up data center power demand in hearings, according to the Let’s Data Science summary, which could shape how many of the eleven plants actually get a reprieve.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Over 20 trillion gallons of rain fell on the Four Corners states and Nevada in two weeks
- 11 engines built to run well past 200,000 miles
- Two Kentucky residents died when a small plane crashed at Missouri’s Lake of the Ozarks, and the NTSB is investigating
- A handful of car transmissions are so tough that mechanics say they almost never die