At about 7:56 a.m. on Wednesday, July 22, a mechanical failure knocked a 230-kilovolt transmission line out of service in Northern Virginia. The line fault itself was cleared normally, but data centers across the region then dropped off the grid in two waves, switching to their own generators, and nearly 3.9 gigawatts of demand vanished at once, the largest such event in the history of PJM Interconnection, the grid operator for 13 states and Washington, D.C.
Four months later, PJM has asked federal regulators for a rule that would let states make data centers pay for the transmission upgrades they cause. The request, filed on Nov. 16, is a proposal and not yet an order.
Two waves of disconnections in the Dominion zone
PJM’s own account of the event, published on its Inside Lines news site, places it in the Dominion zone. A first drop of 2,970 megawatts was followed by a second of 1,099 megawatts, for roughly 3,800 megawatts overall, and PJM’s total load fell from 99,984 to 96,205 megawatts. Reports on the filing, including one from the Daily Caller, describe the drop as nearly 3.9 gigawatts, and the sources do not reconcile the small gap between the two.
The disconnections produced voltage spikes and frequency swings. Operators dispatched generation down and called on reactive power resources to bring voltage back, restored frequency to 60 hertz and recovered the area control error limit within nine minutes, inside the 30-minute standard set by the North American Electric Reliability Corporation, according to PJM. PJM spokesman Jeff Shields said operators “were able to react so that no customers were in imminent danger of losing power.” Earlier events in the same zone, on July 10, 2024 and Feb. 17, 2025, each involved about 1,500 megawatts, so the July 22 drop was more than twice their size.
The Nov. 16 filings: who pays for the wires
The Daily Caller reported that PJM filed two related proposals with the Federal Energy Regulatory Commission on Monday, Nov. 16. The first would give states “transparent access to the costs of transmission improvements driven by data centers,” in line with what FERC directed, so that states can bill customers classed as Large Loads, defined as 50 megawatts or more at a single site. PJM would post the costs of upgrades and what drove them on a publicly searchable page of its website, and states could use their retail rate authority to decide whether particular customers pay. The utilities that own the power lines would propose how to split and recover the costs.
The same filing would halve the expected study period for new power plants and large electricity users. PJM’s description of the “Fast Energization” proposal, posted on Inside Lines, says it would cut the projected study timeline for large users from two years to one, study generation and load together, and move readiness and financial requirements earlier to screen out speculative projects. PJM asked FERC for a 60-day comment period and a decision within 120 days.
Shields cautioned that PJM “does not control how those costs are allocated,” the Daily Caller said, adding that the intent is for data centers to bear the costs of the upgrades they drive. In other words, PJM is supplying the cost information; whether a data center pays would be decided by state regulators and the utilities.
A ride-through rule aimed at the July 22 behavior
The second filing targets what the data centers did that morning. According to CASRAI’s summary of the filing, PJM is asking FERC to approve tariff revisions that create a “Large Computational Load” category for facilities of at least 50 megawatts, of which at least 25 megawatts is served through power electronics, and to require them to ride through voltage and frequency disturbances. Under the proposal, an undervoltage between 0.80 and 0.90 per unit would require a facility to stay connected for 2.0 seconds, and after recovery it would have to restore at least 90% of its pre-disturbance demand within two seconds. PJM asked for a ruling by Jan. 15, 2027. If approved, the rules would take effect Jan. 16, 2027, and existing sites would get one year to comply, per the Daily Caller.
PJM’s Operating Committee chair, Emanuel Bernabeu, said at an Aug. 6 meeting that the data centers involved “should not disconnect from the grid,” as Data Center Knowledge reported. The same article quoted Neil Osnato, founder of Persistence Analytics Group: “A normally cleared grid disturbance should not automatically trigger a second, much larger system disturbance.”
Why the scale matters for PJM’s 67 million customers
The stakes extend beyond a single morning. PJM’s grid serves more than 67 million people, and data centers account for 30 of the 32 gigawatts of peak demand growth PJM projects for 2024 through 2030, according to the Daily Caller’s account of its 2025 forecast. A separate federal track is running in parallel: FERC ordered NERC on July 16 to develop the first phase of enforceable reliability standards for computational loads by Dec. 31, 2026, with minimum voltage and frequency ride-through requirements expected in 2027, per PJM.
The decision now sits with FERC, which has until about mid-March under PJM’s 120-day request to rule on the cost-transparency filing, and until Jan. 15 on the ride-through rule.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Zero Motorcycles unveiled an electric motorcycle targeted at under $8K and a street-legal dirt bike at EICMA
- New FCC rules on how people can stop robocalls and texts take effect Nov. 25
- Neanderthals in Spain carved a wooden object that matches nothing archaeologists have ever found
- The FAA wants $2.39 million from a flight school it says flew a Cessna about 280 times with an unapproved part