For the 3.2 million residents of Puerto Rico, a blackout is a recurring event that the island’s own utility cannot reliably prevent, and the federal government has now extended its emergency response for another three months. The U.S. Department of Energy renewed two emergency orders for the island’s grid on Nov. 6, 2026, and the new terms run from Nov. 8 into the first week of February.

Read next on Morning Overview: 11 engines built to run well past 200,000 miles

The orders are numbered 202-25-1F and 202-25-2F, and the letter F marks the sixth time the department has renewed the pair since May 2025. DOE’s press release, dated Nov. 7, says the orders build on earlier actions taken in 2025 and 2026.

Orders 1F and 2F, in plain terms

Both orders are issued under Section 202(c) of the Federal Power Act, the authority DOE cites for both emergency orders. DOE’s Puerto Rico page says they were first issued on May 16, 2025, to the Puerto Rico Electric Power Authority, known as PREPA, and have been renewed roughly every three months since.

The generation order, 202-25-1F, requires PREPA to operate specified generating units in certain circumstances. The companion 202-25-2F requires vegetation management and asset management so that specified transmission facilities stay operationally available. The department’s page lists the term as Nov. 8, 2026, through Feb. 5, 2027, which is 90 days.

The department’s page describes the generation order’s purpose as “closing the gap in generation shortfall,” and the transmission order’s purpose as reducing shortage and fire risk while keeping the specified transmission facilities operational. Generation capacity and clear corridors are the two levers the orders pull.

Earlier versions were narrower. The original May 2025 generation order and its transmission counterpart covered dispatch and vegetation. Asset management was added in later renewals, according to DOE’s page.

What DOE says the orders let PREPA do

In the Nov. 7 release, DOE said the orders authorize PREPA to dispatch the generation units needed to maintain critical generation capacity, and that vegetation work near power lines continues. The department’s stated reason for the tree work is blunt: “Falling tree limbs and brush can damage transmission lines, cause widespread outages, and potentially cause wildfires.”

Energy Secretary Chris Wright said in the release: “The Department of Energy remains committed to modernizing Puerto Rico’s electric grid.” Governor Jenniffer González-Colón said the department’s 202(c) orders “have provided essential flexibilities to increase generation capacity,” and added that more work remains.

The Rio Times, which summarized the renewal on Nov. 8, reported more detail than the press release carries. By its account, order 1F covers temporary generators supplied by the Federal Emergency Management Agency at San Juan and Palo Seco, with operating limits meant to respect environmental rules. The same account says DOE counted 2,186 miles of line cleared by Oct. 22, 2026, and estimated that clearing the main 115 kV and 230 kV routes could avoid 1.76 million customer interruptions.

Trade publication T&D World, which reported the renewal on Nov. 9, repeated the same core points: dispatch authority for PREPA, continued vegetation management, and DOE’s stated aim of serving the island’s 3.2 million residents together with the governor and local authorities. Neither DOE’s release nor that report names the individual generating units covered by order 1F.

Blackouts, bankruptcy and a generation gap

The Rio Times account of the renewal says DOE described an energy crisis with unstable reserves and widespread blackouts. Since the previous order, it reported, several load-shedding events cut power to at least 50,000 customers. Load shedding is the deliberate rotation of outages when supply falls short of demand, and the report says LUMA Energy, the private operator of the transmission and distribution system, told the island’s regulator that a generation shortfall of several hundred megawatts persists.

That account also lists the causes DOE cites: decades of deferred maintenance, the bankruptcy of the system’s owner and operator, and damage from hurricanes and earthquakes. Repairs, it says, now take years rather than months, slowed by funding approvals, contract disputes and supply-chain problems. These figures come from that secondary summary; the department’s own press release does not carry them.

Six renewals and no end date

DOE’s Puerto Rico page links every version of the orders, and the dates show how routine the extensions have become. The first renewals came on Aug. 14, 2025, and Nov. 12, 2025, followed by Feb. 10, May and Aug. 7 of 2026, and now Nov. 6.

Nothing in the sources reviewed says when the emergency will end. The Rio Times account says the department will keep assessing the grid and will renew the orders while emergency conditions persist, and that DOE did not say what the orders cost or how many outages they will prevent.

The next decision point is early February 2027, when the current term expires on Feb. 5. Whether DOE issues a “G” version then depends on a department assessment that has not been published, and the generation shortfall that LUMA described to regulators remains the open question hanging over that choice.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.


More from Morning Overview

Morning Overview is reader-supported. Some links in our articles are affiliate links, and we may earn a commission at no extra cost to you. As an Amazon Associate I earn from qualifying purchases. Full disclosure.