Holtec International’s paperwork for the Palisades site in Covert Township, Michigan, now describes two plants rather than one. Beside the 1971-era reactor the company is trying to restart, Holtec wants to build two new small modular units, and it has handed the Nuclear Regulatory Commission both halves of the application it needs to start.
Read next on Morning Overview: A flight school faces a $2,388,500 FAA fine for flying an unairworthy plane
The reactors are named Pioneer 1 and Pioneer 2. Each is an SMR-300, a pressurized water design that World Nuclear News puts at about 300 megawatts of electricity, and the company plans to bring them online in the early 2030s.
Part 1: a request to start digging
The application was filed in phases. Holtec’s subsidiary SMR, LLC submitted Part 1 on Dec. 31, 2025, and the NRC published its notice of receipt in the Federal Register on Jan. 22, 2026. That first part sought a limited work authorization, three exemption requests and an environmental report covering construction and operation.
A limited work authorization lets an applicant begin certain early construction before a full construction permit exists. In Holtec’s case the first work is below ground: improving soil in the excavation and pouring foundations for each unit’s containment structure, a shared reactor auxiliary building and an intermediate building for each unit, as Nuclear Newswire reported in January. Holtec asked the NRC to approve the authorization by Dec. 31, 2026.
The same report said Part 2 would follow no later than mid-2027. It came earlier.
The three exemption requests show how much Holtec wanted to do before a full permit. One would permit certain construction ahead of the construction permit. A second would waive the requirement to identify specific funding sources at this stage. A third would allow permanent retaining walls or excavation supports before the limited work authorization is approved, and Holtec asked for a faster six-month review of that one, per Nuclear Newswire.
The Federal Register notice said the applicant planned to file Part 2 within 18 months of Part 1, and that later notices would cover docketing and opportunities for public participation. Nuclear Newswire quoted the NRC as saying detailed technical review would run “not to exceed 18 months” once the staff docketed the filing.
Part 2: the safety analysis lands
On Oct. 2, World Nuclear News reported that Holtec had submitted the Preliminary Safety Analysis Report, which completes the second phase of the construction permit application. Holtec called the filing “the most significant step to date toward establishing the regulatory framework for the Pioneer plant,” according to the same item, and thanked the Department of Energy for backing the program. The Energy Department awarded Holtec $400 million for the SMR plans in early December 2025, Nuclear Newswire said.
Two items remain on Holtec’s side. The company still has to finish a construction cost estimate, a 4D construction simulation of the whole plant and confirmatory safety analyses for the final safety report. And building the units would not be the end of the paperwork: Holtec will need to file a separate operating license application after construction.
NRC steps already taken
The agency’s Pioneer project page, last updated Nov. 19, shows the review moving. Dockets 05000616 and 05000617 cover the two units. An acceptance review letter went out on Feb. 13, a Federal Register notice of acceptance and opportunity for a hearing followed on Feb. 27, and an audit plan was issued March 27.
On June 10 the NRC announced its intent to prepare an environmental impact statement and hold scoping. A draft safety evaluation report dated Aug. 31 is listed as issued with information gaps. On Aug. 28 the commission also granted an exemption allowing permanent excavation-support and cutoff walls at the site, World Nuclear News reported.
The page lists targets rather than decisions. An advanced safety evaluation report with no open items is aimed for Jan. 31, 2027, and the final safety evaluation report and final environmental impact statement for March 31, 2027. World Nuclear News says a safety evaluation report and an environmental assessment are required before the NRC can approve the projects. Nothing on the pages read for this article shows a construction permit or a limited work authorization granted.
Two licenses, one shoreline
The new reactors share an address with a reactor that has not yet delivered power. World Nuclear News lists the existing Palisades unit as an 805 MWe pressurized water reactor that closed in 2022, and the NRC’s Nov. 20 status report shows it at 0% power. The site is 432 acres, according to the NRC project page, and the area affected by the first exemption is about 9 acres.
Holtec has said it will start preparatory civil work once the old reactor is reconnected to the grid, a condition Nuclear Newswire attached to the plan in January when it expected reconnection by the end of February 2026. That date has passed without power.
The open question is sequence. The NRC’s own targets put its final safety and environmental reviews in March 2027, while Holtec’s early-2030s online date for the Pioneer units depends on a construction permit that, on the record read here, the commission has not issued.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- California’s Long Valley supervolcano is quietly sinking, its biggest drop on record
- Up to 5 feet of snow is burying Donner Pass, and forecasters warn against Sierra travel
- Refiners are making less gasoline and more diesel, and here’s why
- The NSA warns phone owners to switch off Bluetooth whenever they aren’t using it