Turkey’s first nuclear reactor just passed the strength and leak tests on its containment

For eight days, engineers at Akkuyu in southern Turkey pumped air into the inner containment building of the country’s first nuclear reactor, held it at pressure, then drew it back down below atmospheric pressure. The point was to find out whether a shell meant to trap radioactive material in an accident would flex as predicted and hold its seal.

Read next on Morning Overview: The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power

It did, according to the plant’s operator, and the result clears one of the last gates before the Russian-built unit is loaded with fuel. The announcement was reported on Nov. 13, and it leaves Turkey’s long-promised end-of-2026 grid target looking tight but still on the table.

Eight days at 0.46 megapascals

The pre-launch trials checked two things in the inner containment of Akkuyu unit 1: strength and leak tightness. According to World Nuclear News, air pressure inside the building was raised to 0.46 megapascals, a load equal to roughly 47 tonnes on every square metre of containment surface. Pressure was then lowered in stages, all the way to below atmospheric, while engineers recorded stresses in the structure and any change in its shape and dimensions under load.

Leak-tightness measurements were taken at both the elevated and the reduced pressure, which matters because a shell can behave differently when pushed outward than when pulled inward. The operator, Akkuyu Nuclear JSC, is credited with running the program, and no independent inspector or outside testing contractor is named in the report.

Sergei Butckikh, chief executive of Akkuyu Nuclear JSC, said the results confirm the high quality of the containment construction work. He added that they allow the project to move shortly to the next pre-start-up stage, cold and hot functional testing of the reactor plant.

Operators of any pressurised reactor want that kind of evidence on paper before nuclear fuel arrives, because a containment that is found to leak after fuel loading is far harder to fix than one found to leak beforehand. The sequence at Akkuyu follows that logic: mechanical proof of the building first, then proof that the reactor plant works at temperature, then fuel. The report does not say how the measured deformation compared with design predictions, so the numbers behind the pass are not public in this account.

Two containments around one VVER-1200 reactor

The VVER-1200 design that Rosatom is building at Akkuyu uses a double containment. The inner building protects the main reactor equipment and is designed to prevent any release to the environment. The outer building is reinforced concrete and shields the unit from extreme external events. Only the inner shell takes the pressure test described above, since it is the one expected to contain an internal accident.

Akkuyu sits in Mersin province on Turkey’s Mediterranean coast. Rosatom is constructing four VVER-1200 units there under a build-own-operate model, and at 4,800 megawatts of electricity in total the plant is expected to meet about 10 percent of Turkey’s electricity needs.

The test sequence since June

The containment trial is one rung in a ladder that began months ago. Cold hydraulic tests started in June after dummy fuel was loaded, checking that safety-related components were installed correctly and that the primary circuit held tight. Rosatom chief executive Alexey Likhachev said then that only a few weeks remained before commissioning operations would begin, according to a report from Czech outlet Oenergetice on the unit’s completed construction.

Hot hydraulic tests followed. World Nuclear News reported on Oct. 9 that the primary circuit was filled with demineralised water and pressurised to 24.5 megapascals, about 1.5 times normal operating pressure, with water temperature reaching 135 degrees Celsius at the initial stage. Likhachev called the results a convincing confirmation of installation, welding and commissioning quality, and the automated process control system was commissioned during that work.

The next stage, hot functional tests, will confirm that equipment is ready for operating conditions, including the four main circulation pumps running at temperatures of at least 260 degrees Celsius. Nuclear fuel loading and physical start-up come only after the cold and hot test programs are finished. No dates have been given for any of these stages.

Akkuyu Unit 1’s remaining milestones

The history is long. A 2010 intergovernmental agreement between Russia and Turkey set a target of commissioning unit 1 within seven years of receiving all construction permits. The construction licence was issued in 2018, when building began, and fuel arrived at the site in April 2023. Rosatom announced that construction of the unit was complete before the test campaign began. The goal now is for unit 1 to start supplying Turkey’s grid by the end of 2026.

Turkey is already looking past Akkuyu. World Nuclear News notes that a second plant is planned at Sinop, that talks with China about a third plant in Thrace are under way, and that Energy Minister Alparslan Bayraktar told Bloomberg talks with Canada and South Korea on new projects continue. On Nov. 12, Candu Energy and Türkiye Nükleer Enerji Anonim Şirketi signed a memorandum of agreement for a feasibility study of a potential 4.5-gigawatt plant with up to six Candu reactors.

What remains unanswered is the calendar. With the containment cleared, cold and hot functional testing, fuel loading and the first chain reaction all still lie ahead, and neither the operator nor Rosatom has published dates for them.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.