When a test reactor reaches criticality, the milestone is often the end of its story: the machine is studied, taken apart and replaced by the next design. Oklo’s first reactor is getting a longer life instead.
Read next on Morning Overview: 11 engines built to run well past 200,000 miles
The company says its Groves-1 reactor in Lockhart, Texas, has received Department of Energy approval to move from its initial demonstration status to an “operating platform for research, testing, and training.” For a startup trying to prove it can build and run reactors on a commercial schedule, a working machine it can keep using is worth a great deal.
Groves-1 moves past its demonstration status
According to the American Nuclear Society’s Nuclear News, the change was the most notable of several updates Oklo released over the past week in press releases, social media posts and its third-quarter results presentation. Groves-1, also called the Groves Isotope Test Reactor, is now “cleared for unrestricted operations” by the DOE, and Oklo plans to use it to “test its capabilities relevant to future isotope reactors and Oklo’s fast fission reactors, the Aurora Powerhouse.”
The work has already started. During a recent startup, Oklo said, operators wore eye-tracking glasses that recorded what they looked at and for how long. The company says the data will be used to “improve the facility’s human-machine interface and inform future design choices.” That kind of study is only possible with a reactor that keeps running and a crew that keeps operating it.
Not every company in the same program has taken that route. Fellow participant Antares completely disassembled Mark-0, the reactor it used to reach criticality, to clear the way for its next design, Mark-1, which will be built in the same facility at Idaho National Laboratory. Bob Boston, manager of the DOE’s Idaho Operations Office, announced that the teardown milestone had been met.
A pool-type reactor born under an executive order deadline
Groves-1 exists because of the DOE’s Reactor Pilot Program. President Trump’s Executive Order 14301, signed in May 2025, told the department to create a pathway for companies to win DOE authorization for first-of-a-kind test reactors, and set a goal of three reactors reaching criticality by July 4, 2026. Antares Nuclear, Valar Atomics and Deployable Energy hit that mark before the deadline.
The pilot program was built as a one-shot selection of 10 companies, named in August 2025, whose projects could become eligible for DOE authorization instead of the usual Nuclear Regulatory Commission licensing path. Aalo Atomics added a fourth criticality in the early hours of July 4 itself. Most of the early reactors sit at Idaho National Laboratory, while Valar Atomics built its machine at the state-owned Utah San Rafael Energy Lab.
Oklo’s reactor followed on August 5. Nuclear News reported that the pool-type, water-cooled, nonpressurized reactor reached criticality at 9:19 p.m. Eastern time, making it the fifth DOE-authorized reactor to do so and the first on private land, at a greenfield site. “Reaching criticality in less than a year is an incredible milestone for [the] team,” Oklo cofounder and CEO Jacob DeWitte said at the time.
The reactor belongs to Oklo Isotopes, the unit formed after Oklo bought radioisotope producer Atomic Alchemy in 2025. Oklo has described Groves as a test platform for future production-scale isotope reactors serving health care, industry, research, space and national security. In October, the company laid out plans for a follow-on Groves-2 project focused initially on medical isotope production, enabled by the DOE’s newer Nuclear Energy Launch Pad program.
Aurora concrete, uranium contracts and a forging deal
The research reactor is a sideline to Oklo’s main business, the Aurora Powerhouse, a 75-megawatt-electric liquid metal-cooled, metal-fueled fast reactor. On November 11, Oklo said structural concrete and steel are in place at its Aurora site at Idaho National Laboratory. The project has DOE approval of its preliminary documented safety analysis, the third of five approval milestones, and still needs a documented safety analysis and a final readiness review before startup. Oklo’s third-quarter update says it plans to install major reactor components within the next 12 months.
Fuel is the other constraint. Oklo has signed what it calls “multiple definitive, multiyear contracts” with Centrus Energy for high-assay low-enriched uranium, including prepayments to support new enrichment capacity at the American Centrifuge plant in Ohio, with deliveries scheduled to begin in 2029. Oklo plans to use that fuel for the refueling of Aurora-INL and for a planned 1.2-gigawatt plant in Ohio, part of a deal under which Meta could support as many as sixteen Oklo reactors.
The company also signed a manufacturing agreement with U.S. Forged Rings, an ultra-heavy steel forging firm, with initial component deliveries expected in 2030. Oklo’s update describes the deal as “27 Aurora module-equivalents reserved across 2030–2035.” Groves-1 is the only Oklo reactor running today; the forging reservation shows how many more the company expects to build.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- A $1 billion gas plant planned for Superior, Wisconsin, has been abandoned
- Shaq spent $1.3 million on three Rolls-Royce Phantoms to prove a point to a salesman
- The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power
- Over 20 trillion gallons of rain fell on the Four Corners states and Nevada in two weeks