Four decades after workers first poured concrete for it, the last unfinished reactor at Slovakia’s Mochovce plant is now running at more than a third of its rated output. Slovenské elektrárne, the country’s largest power producer, announced on Nov. 12 that the 471-megawatt unit had been raised to 35 percent of reactor power.
Read next on Morning Overview: Over 20 trillion gallons of rain fell on the Four Corners states and Nevada in two weeks
The step is part of a staged ladder that ends with a 144-hour continuous run at full power. Between here and there sit four more power plateaus, each with its own battery of tests and a regulator watching the results, and each one a chance for the schedule to slip again.
The 35 percent plateau and what follows
Martin Mráz, the project director for completing the Mochovce units at Slovenské elektrárne, said that by achieving 35 percent the team was entering the next part of the energy start-up programme. World Nuclear News reports that checks at 35 percent come first, after which power is raised to 55, then 75, then 90 percent and finally 100 percent. Each level has its own test range, and a higher level follows only after the results are evaluated.
The final examination is the 144-hour trial at full power. Only after it is completed successfully can the unit be considered fully functional at its 471-megawatt design capacity. Its sister unit, Mochovce 3, entered commercial operation in October 2023, and the 144-hour run is the same kind of trial that unit faced before it was declared fully functional.
Once running at full output, unit 4 is expected to generate about 3.5 terawatt-hours a year, roughly 13 percent of what Slovakia currently consumes, according to Slovenské elektrárne’s own figures as reproduced by Enerdata.
From criticality in August to grid connection in October
The reactor reached first sustained criticality on Aug. 6, an event the American Nuclear Society covered in mid-August. Power generation began at 15:33 on Monday, Sept. 21, a point the operator described as the last major stage before the unit is put into operation, as World Nuclear News detailed in its start-up report. The Nuclear Regulatory Authority of the Slovak Republic inspected the plant and reviewed documentation before it approved that stage.
Connection to the national grid was supposed to happen on Tuesday, Oct. 13, with Prime Minister Robert Fico scheduled to attend. Slovenské elektrárne spokesperson Lenka Šarláková said the connection was postponed because of the need to repeat a technical test of the unit, according to Oenergetice, and the company said it would connect in the coming days.
It happened on Thursday, Oct. 15, at 20:41. In its press release, the company said one of the two turbine generators was synchronised with the transmission system while the reactor ran at 20 percent power. Chief executive Branislav Strýček said that for the first time in its history, Mochovce 4 was supplying electricity to Slovakia’s power system. Mráz added that the moment lasted only a short time but was made possible by the coordinated work of many professions. The second turbine generator was still to be synchronised at that point, a step World Nuclear News also covered when the unit first reached the grid. Power then continued upward through the plateaus: the stated sequence in the start-up programme runs 5, 20, 35, 55, 75 and 90 percent before full output, with the unit joining the grid at 20 percent. The sources reviewed do not say whether the second generator is online at 35 percent.
A plant finished in stages since 1982
Mochovce is a story of long gestation. Construction of units 1 and 2 began in 1982, and those two reactors entered operation in 1998 and 1999. Work on units 3 and 4 started in 1986 but stalled in 1992. The effort to finish them restarted roughly a decade ago at an estimated cost of EUR 6.7 billion, or about $7.6 billion in U.S. dollars.
Slovakia’s five operating reactors supply over 60 percent of the country’s electricity, two of them at Bohunice. Slovenské elektrárne itself produces about 66 percent of national power, and closed its last coal-fired plant in the first quarter of 2024. Majority ownership of the company sits with Slovak Power Holding, part of the Czech energy group EPH, while the Slovak Republic holds 34 percent.
When the last unit is finished, Slovakia is expected to keep or extend its position as the country with the highest nuclear share of electricity. Longer term, the government has agreed with the United States on a one-gigawatt reactor at the Jaslovské Bohunice site, according to Enerdata, and is reported to be weighing small modular reactors.
The open question for the next stretch is pacing. The October delay showed that a single repeated technical test can move a politically staged milestone by days, and the remaining plateaus at 55, 75 and 90 percent each carry the same possibility. Neither the operator nor the regulator has published a date for the 144-hour run or for commercial operation.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- The FAA wants $2.39 million from a flight school it says flew a Cessna about 280 times with an unapproved part
- A $1 billion gas plant planned for Superior, Wisconsin, has been abandoned
- Shaq spent $1.3 million on three Rolls-Royce Phantoms to prove a point to a salesman
- The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power