A reactor that Ontario has been counting on to anchor a new generation of small nuclear plants has slipped off its own schedule before it has produced a single watt. On Nov. 10, Ontario Power Generation told investors that Unit 1 at its Darlington site, east of Toronto, is no longer expected to begin commercial operation by the October 2030 target the company had previously disclosed.
Read next on Morning Overview: Shaq spent $1.3 million on three Rolls-Royce Phantoms to prove a point to a salesman
The same notice said the project is also no longer expected to finish within the previously disclosed estimate of C$7.7 billion, roughly $5.4 billion in U.S. dollars. That figure covers the first unit plus the systems and services shared by every reactor planned for the site. No replacement date or dollar amount came with the announcement.
What OPG disclosed in its third-quarter results
The disclosure sat inside the utility’s 2026 third-quarter financial results, released on Nov. 10, rather than in a standalone announcement. The release says Unit 1 is not expected to hit the October 2030 commercial-operation date or stay inside the C$7.7 billion estimate, and it ties both problems to ongoing engineering for GE Vernova Hitachi Nuclear Energy’s first-of-a-kind small modular reactor. That engineering, according to OPG, is affecting how construction is carried out and how the supply chain performs.
Nicolle Butcher, OPG’s president and chief executive, said in the release that the company has made meaningful progress on the first small modular reactor in the G7 and that work continues daily on site. She also said OPG has identified risks that will affect Unit 1’s schedule and budget, and that the company is working to assess those effects and settle on a cost and schedule outlook it can stand behind.
OPG is working with the vendor to finish the outstanding engineering scope. World Nuclear News reported on Nov. 11 that a GE Vernova Hitachi spokesperson, quoted by The Globe and Mail, pointed to several interconnected factors across engineering, procurement and construction, plus market conditions.
A new estimate is not due until mid-2027
Anyone looking for a corrected number will wait. OPG says it expects to substantially complete a comprehensive assessment of projected cost and schedule by mid-2027, roughly seven months from now. The review is meant to weigh how complete the engineering is, how mature the design is, the complexity of building a reactor type for the first time, inflation, geopolitical risk, the risks that remain, and whether mitigation and recovery measures are working.
Until then the only firm statement is a negative one. OPG says it intends to provide further updates as additional material information becomes available, which leaves the project in an unusual position: a unit under active construction with a lapsed date and a lapsed budget but no successor to either.
Canary Media’s Dan McCarthy, in a report on the delay, described this as the project’s second schedule slip. When the design was announced in late 2021, completion was expected as early as 2028, so the October 2030 target already represented a retreat. The same report notes that the C$7.7 billion budget covered a unit whose cost OPG now expects to exceed.
Four reactors, C$20.9 billion, and a fleet-sized bet
Unit 1 is the first of four BWRX-300 reactors planned at Darlington, each rated at 300 megawatts of electricity. In May 2025 Ontario approved a C$20.9 billion budget for the four-unit program and the start of construction on the first, a sum that World Nuclear News broke down in a separate explainer on how the figure is built. The Canadian Nuclear Safety Commission had granted a licence to construct the first unit the month before. Federal and provincial governments have also committed up to C$3 billion for minority stakes in the project, according to Canary Media.
The province has said the program will support up to 18,000 jobs and add C$500 million a year to the economy, and that 80 percent of spending will stay with Ontario companies. Those claims now rest on a first unit whose price is being re-measured. The C$20.9 billion total is a separate envelope from the C$7.7 billion first-unit figure, and OPG has not said whether the larger budget is affected.
The reactor is also a reference plant for other buyers. The Tennessee Valley Authority received a construction permit from the U.S. Nuclear Regulatory Commission for a BWRX-300 in September, and a Texas developer, Blue Energy, has begun an application for another, Canary Media reports. Delay and overrun at the first-built unit is the data those customers will study.
What has actually been built at Darlington
The delay arrives alongside real construction progress. OPG’s quarterly release lists the completed assembly of the tunnel boring machine, with tunnelling for the condenser cooling water tunnel expected to start in the fourth quarter of 2026, and the first pour of the turbine building. It also credits the installation of a 2.1-million-pound basemat, which the company calls the first nuclear foundation laid in Canada in more than 30 years.
World Nuclear News adds that site preparation began in autumn 2022, that long-lead items including the reactor pressure vessel have been procured, and that the basemat went in 35 metres below ground in April. The American Nuclear Society’s June coverage of the site frames the project as North American construction returning to a smaller, faster format.
The open question is how much of the slip is schedule and how much is money. OPG has quantified neither, and says the answer will come from the assessment due by mid-2027.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- New FCC rules on how people can stop robocalls and texts take effect Nov. 25
- Neanderthals in Spain carved a wooden object that matches nothing archaeologists have ever found
- The FAA wants $2.39 million from a flight school it says flew a Cessna about 280 times with an unapproved part
- A $1 billion gas plant planned for Superior, Wisconsin, has been abandoned