PSEG and Constellation plan a 200-MW nuclear uprate at New Jersey’s Salem plant

Salem Generating Station, a two-reactor nuclear plant in southern New Jersey, already produces more than two gigawatts. Its owners now plan to squeeze about 200 more megawatts out of it without building a new reactor.

PSEG Power and Constellation Energy plan a roughly 200-MW uprate at Salem, Utility Dive reported on Nov. 3, 2026, citing PSEG’s third-quarter earnings presentation. PSEG Power’s share would be about 112 MW, with the remainder falling to Constellation.

What PSEG’s earnings materials say about the 200 MW

Ethan Howland of Utility Dive wrote that Salem’s current installed capacity is 2,280 MW, which puts the planned increase at roughly nine percent of today’s output. The ANS Nuclear Newswire gave the unit ratings behind that total: Salem Unit 1 at 1,146 MWe and Unit 2 at 1,139 MWe, with Constellation holding 43 percent of the plant and PSEG Nuclear 57 percent.

Neither report gives a construction schedule. PSEG’s chief financial officer, Daniel Cregg, did offer an outer boundary on the Nov. 2 earnings call, according to a Motley Fool transcript carried by Nasdaq: the Salem project is in the company’s five-year plan and will be online by the end of that period, which runs to 2030. The transcript warns it may contain errors, so the date is best read as a company target, not a licensed milestone.

Chief executive Ralph LaRossa tied the work to the latest Constellation deal on the call, describing it as covering upgrades at Salem that PSEG has been enabling.

Who gets which megawatts, and what the power is for

Utility Dive linked the uprate to a recently announced nuclear power purchase agreement with Google and to PSEG Power’s talks with data center operators. LaRossa said PSEG Power is “continuing to develop terms with large load entities,” a reference to contracts that could cover existing nuclear output, future upgrades and other generation.

The other half of the uprate shows up in Constellation’s numbers. On its own Q3 call on Nov. 12, Constellation reported agreements with three customers covering 4,560 MW, of which 1,165 MW is new nuclear capacity from ongoing and planned uprates, ANS reported. The uprates are expected to cost $4.3 billion, about $1.3 billion of it in 2026 and 2027 and about $3 billion from 2028 through 2032. ANS’s account of that call does not break out Salem, so the Salem megawatts cannot be separated from the 1,165 MW total.

Joe Dominguez of Constellation said on that call that the company has not finished exploring uprates at its plants and that design and engineering work continues.

No uprate application at the NRC yet

An uprate of this size needs a license amendment from the Nuclear Regulatory Commission. No Salem application for the 200-MW increase appeared in the reports reviewed, and neither Utility Dive nor ANS mentions NRC review of it. The company’s recent contact with the agency concerns something different: ANS reported that PSEG notified the NRC of its intent to seek 20-year license extensions for both Salem and Hope Creek.

World Nuclear News, covering PSEG’s March 28, 2024 notice, gave the details. Salem 1’s license expires in 2036 and Salem 2’s in 2040, and renewals would carry them to 2056 and 2060. Hope Creek’s would move from 2046 to 2066. PSEG expected to submit the application in the second quarter of 2027, with NRC review taking about two years.

Salem has been through this before. The NRC’s record of earlier Salem uprates shows a request submitted Nov. 10, 2000 and approved in a license amendment issued May 25, 2001, raising licensed thermal power from 3,411 MWt to 3,459 MWt. That 48-MWt step, about 1.4 percent, took roughly six months from filing to approval and is far smaller than the 200 MW now planned.

A refueling outage that has not ended

The expansion plan sits beside an operating problem. PSEG disclosed that during Salem Unit 1’s scheduled fall refueling outage, a visual inspection found degradation of the thermal shield inside the reactor vessel. In the company’s words, further testing “is ongoing and is expected to extend the refueling outage,” and the effect depends on timing, inspection results and any repairs.

The unit had just completed a 491-day run from breaker to breaker, and PSEG Power’s nuclear fleet posted a 95.5 percent capacity factor in the third quarter, up from 92.4 percent a year earlier. LaRossa said the site’s early site permit gives it an advantage in New Jersey’s nuclear plans, though on the question of new state action he said only that “New Jersey continues to have the conversations.” On the Nov. 2 call he added that PSEG Nuclear attended the first meeting of the governor’s nuclear task force in early October and that the first concrete state step would be a Board of Public Utilities auction for new nuclear, as legislation passed last year calls for.

The plan’s open questions are concrete: whether an NRC application is filed, when Salem 1 returns from its extended outage, and how much of Constellation’s 1,165 MW comes from Salem.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.