Northern Illinois is projected to run short of power before the rest of the state, and a nuclear developer in Iowa has now said it is looking at an underground cable as a way to get electricity there. The company, ONE Nuclear Energy, has no site, no reactor design and no buyer for a plant of up to 1,000 megawatts that it calls Project Northern Pike, but it has signed a letter of intent to explore using a planned buried line to Illinois.
Both halves of the idea are still on paper. The plant is at the site-screening stage, and the line, called SOO Green, has not been built.
Project Northern Pike and what is missing from it
Interesting Engineering reported on Nov. 19 that ONE Nuclear is evaluating sites in Iowa for a proposed 1,000-megawatt plant that could produce firm, carbon-free electricity, with first power targeted for the mid-2030s. According to the article, no site, reactor design or power purchase agreement has been selected, and site screening and technology evaluation are under way.
The project would need federal licensing from the Nuclear Regulatory Commission, transmission and grid studies, financing and offtake agreements, the article says, and it describes the link as a potential route to market rather than a guarantee that the plant gets built.
ONE Nuclear, which trades on Nasdaq under the symbol ONEN, is pursuing the project in a state that has been organizing around nuclear power. Gov. Kim Reynolds created a state nuclear task force in January 2026, and its 130-page final report, released Sept. 3, recommended a statewide feasibility study and a “nuclear-ready” program for interested communities, according to the American Nuclear Society’s news summary. The same summary reports that on Sept. 8, NextEra Energy and DOE’s Office of Energy Dominance Financing announced a loan of up to $1.9 billion to restart the Duane Arnold plant in Linn County, Iowa, which shut down in 2020, with restart targeted as early as 2029. That restart is a separate project from Northern Pike.
The letter of intent with SOO Green
The agreement was announced Nov. 5 in a press release carried on Finviz. SOO Green HVDC Link, developed by energyRe and Copenhagen Infrastructure Partners, and ONE Nuclear signed a non-binding letter of intent to explore delivering nuclear energy and capacity into the PJM Interconnection over SOO Green’s line. The release says future commercial arrangements depend on definitive agreements and on development, regulatory and financing requirements, and that there is no assurance the agreements will be signed or the projects will proceed.
Interesting Engineering adds that the letter does not reserve transmission capacity or commit either party to a final deal, and that the two projects must advance independently. The release says the letter includes certain exclusivity provisions for nuclear generation development.
Coen Weddepohl, ONE Nuclear’s chief investment officer, said in the release that the company expects the project to bring a substantial new source of firm, dispatchable, carbon-free power. SOO Green’s chief executive, David Pacyna, said “SOO Green was built to be that kind of infrastructure.”
The line, the route and the timetable
As described in the release and in Interesting Engineering, SOO Green is a 2,100-megawatt underground high-voltage direct-current line of about 350 miles from Mason City, Iowa, to Yorkville, Illinois, running mostly along existing railway corridors. The developers target commercial operation in 2032, with construction as early as 2028 and permitting expected by the end of 2026, which would put the cable in service years before any nuclear plant could deliver power.
Utility Dive’s September 2025 report on the line described it as a 525-kilovolt design linking the MISO and PJM markets, with the developers saying they held all route rights. It listed interconnection approval from both grid operators as a key hurdle, and said the developers were pursuing PJM’s State Agreement Approach with the Illinois Commerce Commission. That report was published well before the nuclear letter, and its status details are as of that date.
The destination matters to the pitch. The release says the line would add transfer capability into ComEd’s territory in northern Illinois, where the earliest shortfall risk is projected, and cites a December 2025 Illinois report warning of shortfalls in northern Illinois by 2029 and statewide by 2031. That is the same state resource adequacy work behind this month’s draft mitigation plan from the Illinois Power Agency and Illinois EPA, published Nov. 16 and open for comment until Jan. 15, 2027, which proposes keeping some gas and oil plants running past their planned closures.
The release also quotes projected PJM capacity prices of $732 per megawatt-day for 2033 and $872 for 2034 as part of the case for adding supply, and says the line could serve about 1.5 million homes in Illinois and add $3.2 billion in economic activity during construction. Those are the developers’ figures and have not been independently tested in the sources reviewed. The release names Siemens Energy, Jingoli Power, PPL Corporation and Prysmian Group as partners in the SOO Green effort.
Whether Iowa ends up with a reactor at all is the unsettled part. The letter explores access; it does not name a site, a technology or a customer.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- The FAA wants $2.39 million from a flight school it says flew a Cessna about 280 times with an unapproved part
- A $1 billion gas plant planned for Superior, Wisconsin, has been abandoned
- Shaq spent $1.3 million on three Rolls-Royce Phantoms to prove a point to a salesman
- The Justice Department asked courts to undo approvals for three offshore wind farms, one already making power