The cooling towers at Duane Arnold were among the parts damaged when a derecho hit the Iowa plant in 2020, and the reactor never ran again. Now NextEra Energy, the plant’s owner, is working against a calendar that ends in early 2029, when it wants the single boiling water reactor in Palo back on the grid.
Read next on Morning Overview: Microsoft says its November Windows security updates are breaking printing for some users
The Department of Energy put real money behind the target in September: a loan of up to $1.9 billion, closed on Sept. 8. Whether the date holds depends on a list of federal approvals, inspections and construction milestones that stretches across the next two years.
The money and the buyer
DOE’s Office of Energy Dominance Financing closed the loan to NextEra to help finance the restart, World Nuclear News reported on Sept. 8. The restart would add 615 MWe of baseload power, which DOE says is enough for nearly 500,000 homes, and DOE projects about 1,500 jobs during construction and more than 450 once the plant operates.
The reason the project exists is a customer. NextEra announced in October 2025 that it would restart the plant by early 2029, and the economics rest on a 25-year power purchase agreement with Google. NextEra Chairman and CEO John Ketchum said “Restarting Duane Arnold is about delivering new power to meet new demand.”
A DOE spokesperson told Utility Dive that the loan will be repaid with interest and that “hyperscalers, not taxpayers, are paying for the new power generation.” Deputy Secretary of Energy James Danly, in the DOE announcement as reported by World Nuclear News, said the project “will drive down electricity costs.”
Approvals still pending at the NRC
Money does not restart a reactor; the NRC’s Duane Arnold facility page shows why. The plant is still listed in SAFSTOR, a decommissioning status, and all of its fuel was removed from the reactor in 2020 and sits in dry casks on site. The operating license expires Feb. 21, 2034 as listed.
The agency created a Restart Panel and has been accepting NextEra’s requests one at a time. An exemption from certain decommissioning requirements was submitted Jan. 23, 2025 and accepted that February. A request to revise the operating license and technical specifications was submitted Nov. 20, 2025 and accepted on Dec. 15. A security plan update followed Dec. 17 and was accepted Jan. 30, 2026, and an emergency plan reinstatement was submitted Jan. 30 and accepted March 9.
On the environmental side, a draft environmental assessment and draft finding of no significant impact were issued July 30, 2026, with public comment closing Sept. 2. The final versions were projected for fall 2026 on the page, which was last updated Sept. 14, and the NRC’s preliminary view is that a full environmental impact statement is not needed.
At an April public meeting in Cedar Rapids, NRC project manager Justin Poole said the agency expects to issue the licensing actions before January 2028, according to the American Nuclear Society’s account. That leaves roughly a year between the last paper approval and the 2029 target.
The inspection-and-hardware stretch
The same ANS account says April Nguyen leads the NRC restart team, and that inspections focus on pumps, valves, piping, reactor vessel structural integrity and radiation protection. NRC Region III has published an inspection plan, and inspections are scheduled for 2026 with some already set for 2027. The NRC page lists restart inspection reports issued Dec. 11, 2025 and Jan. 12, 2026 and an activity plan dated March 11, 2026.
Local support was on record at that meeting. Barbra Solberg of the Cedar Rapids Metro Economic Alliance said “the economic impact of the restart will be immense.” NextEra cites a 2025 study that projects more than $9 billion in economic benefits for Iowa over 25 years.
The company says it is carrying out inspections, engineering evaluations and operational readiness work under oversight of the NRC and other agencies, and Iowa regulators have already acted: the Iowa Utilities Commission issued a certificate authorizing construction and operation in June, per Nuclear Engineering International.
Two other restarts set the comparison
Duane Arnold is not the first plant to try this. Constellation is restarting the 835-MW Crane plant, the former Three Mile Island Unit 1, at an expected cost of about $1.6 billion, according to Utility Dive, and Holtec is attempting the same at Palisades in Michigan, where fuel is loaded and no power flows. ANS described Duane Arnold as the third U.S. plant to move from decommissioning back to operation.
Sources differ on the plant’s size, with 601 MWe cited by one industry profile and 615 MWe by DOE and ANS; the DOE figure is used here. Both put the restart in the first quarter of 2029 or “early 2029.” The open item that matters most, according to the NRC’s own page, is the final environmental finding and the licensing actions that must land before January 2028.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- A flight school faces a $2,388,500 FAA fine for flying an unairworthy plane
- Ocean mud suggests Cascadia and the San Andreas fault have broken within hours of each other
- 11 engines built to run well past 200,000 miles
- A dangerous unpatched Windows exploit is now public and can hand attackers full control