From Louisiana to Minnesota, utilities in the middle of the country are fielding requests to connect data centers that use as much power as small cities. The organization that runs the region’s high-voltage grid has now told federal regulators how it intends to handle them.
Read next on Morning Overview: The FAA wants $2.39 million from a flight school it says flew a Cessna about 280 times with an unapproved part
The Midcontinent Independent System Operator, known as MISO, has filed what RTO Insider described on November 17 as an “all-encompassing response” to a Federal Energy Regulatory Commission order on how large loads such as data centers connect to the grid. The filing, in FERC dockets ER27-526 and ER27-527, is MISO’s answer to a demand from Washington that it either justify its existing rules or rewrite them.
FERC’s order to six grid operators
The filing, first reported by RTO Insider, closes out months of work. The filing traces back to June 18, when FERC issued tailored “show cause” orders to each of the six regional grid operators it regulates: PJM, MISO, Southwest Power Pool, California’s CAISO, ISO New England and the New York ISO. In FERC’s announcement, the commission directed each operator and its transmission owners to “justify or reform the rules that govern how data centers, manufacturing facilities, and other large energy users connect to the electric grid,” noting that a one-size-fits-all solution would not work across regions as different as New England and the Great Plains.
The orders laid out five categories of reform. According to an analysis by the law firm Morgan Lewis, they include clearer study procedures for large loads, protections to keep the cost of grid upgrades from shifting onto other customers if a data center never materializes, rules for power plants built alongside large loads, new transmission service options for loads willing to limit how much power they draw at peak times, and interconnection options for generators that agree to match their output to a nearby large customer. FERC said it could take more direct action if the responses fell short.
The orders followed an October 2025 Department of Energy directive asking FERC to write rules for the “timely, orderly, and non-discriminatory” interconnection of large loads. FERC also required each operator to report how it would ensure enough generation exists to serve both existing customers and new large loads.
MISO’s 50-megawatt line and reliability rules
MISO built its response in pieces. On August 28, it asked FERC to approve a set of reliability requirements that large loads must meet before connecting, Utility Dive reported. The proposal defines a “large load” as one above 50 megawatts, and a “computational load” as a large load with at least 25 megawatts of demand from servers, storage and networking equipment.
The separate data center category exists because computing loads behave differently from factories. “Computational loads may exhibit rapid and coordinated changes in demand, significant power-electronic behavior, and distinct responses to transmission system disturbances,” MISO told FERC. Its reliability proposal requires detailed modeling data, high-resolution phasor measurement units to monitor facilities during disturbances, limits on how fast data centers can ramp their demand up or down, and “ride-through” standards so they do not drop offline en masse when grid voltage or frequency wobbles. Grid operators in Texas and the PJM region have adopted similar rules after incidents in which data centers suddenly tripped offline.
In August, MISO said its later filings, due by a November 16 deadline, would add new transmission products and study processes, protections against cost shifts, and rules for generation serving “electrically proximate” large loads. The November filing, which RTO Insider called all-encompassing, is the response MISO said would cover those remaining pieces.
Other regions have already shown what such rules can look like. In January 2026, FERC accepted Southwest Power Pool’s High Impact Large Load process, which sets new study and operating requirements for large loads and is designed to support interconnection decisions within 90 days, according to a summary by the law firm Orrick. FERC’s June orders credited SPP and PJM for that earlier work, a signal of the bar MISO’s filing will be measured against.
Why the Midwest’s rules matter
For two decades, electricity demand in MISO’s footprint barely moved. Demand grew about 0.5% a year on average between 2009 and 2024, MISO told FERC, but the operator now expects 1% to 2% annual growth through 2044, with faster growth in the near term. Much of that comes from data centers, including projects like Meta’s planned complex in Richland Parish, Louisiana.
How MISO writes these rules will decide who pays when a utility builds new lines and power plants for a data center, and what happens if the customer walks away. The cost-shift protections FERC asked for are aimed squarely at that risk for ordinary ratepayers. Interested parties, including utilities, data center developers and consumer advocates, can now file comments at FERC, and the commission will decide whether MISO’s proposals are just and reasonable or need changes. Until FERC rules, the request lines for new large loads across the Midwest keep growing under the old process.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Cadillac cut the price of its cheapest EV, which goes up to 317 miles on a charge
- Winter weather advisories cover I-80, I-70 and the Bighorns with up to 15 inches of snow
- Arizona’s governor declared a statewide emergency after Flagstaff logged its wettest Nov. 1 on record
- Zero Motorcycles unveiled an electric motorcycle targeted at under $8K and a street-legal dirt bike at EICMA