Anyone waiting to watch Americans walk on the Moon again by the end of the decade has been handed a schedule with a detour in it. The mission once planned as the first landing, Artemis III, will instead stay in orbit around Earth, with its four astronauts testing whether they can dock with the machines that are supposed to take their successors down to the surface.
NASA laid out the revised plan at an Oct. 23 briefing: Artemis III in mid-2027, landings on Artemis IV and V in 2028.
An Apollo 9 for the lander era
Aerospace America reported that Artemis III was converted in late February into a low-Earth-orbit demonstration, modeled loosely on Apollo 9. NASA’s Artemis III mission page, last updated Oct. 19, says the flight will take place in Earth orbit rather than on the Moon, with objectives meant to prove the systems needed for landings beginning with Artemis IV. Orion will rehearse rendezvous and docking, and NASA also plans to test one or both Human Landing Systems.
The profile, as Aerospace America reported from the briefing, runs about two weeks. Artemis program manager Jeremy Parsons described it this way: Blue Origin’s Blue Moon test article launches first, followed by Orion. On Day 3, Orion docks with Blue Moon, and two astronauts enter the lander cabin over two days of crew operations to evaluate life support and other systems. On Day 6, a Starship test article launches from Florida, Orion undocks and docks with it for about two hours. The remaining days go to further tests, including the Orion Crew Survival System suits.
Nobody goes inside Starship, SpacePolicyOnline reported, and Blue Moon Mark 2 can loiter in orbit for up to 30 days. Orion will fly on the Space Launch System with a spacer in place of the upper stage used on Artemis II. The crew has not been named in the sources reviewed.
Why the Moon landings slid to 2028
NASA said in an Oct. 23 release that it aims to return astronauts to the lunar surface in 2028, with a second crewed landing opportunity to follow, and that it will pick which provider flies first based on lander readiness. Administrator Jared Isaacman, in the same NASA statement, said the agency has a proven foundation in the Space Launch System and Orion, along with two lunar landers in development with Blue Origin and SpaceX.
Parsons told the briefing that “regardless of who goes first, both providers are planning for lunar landing missions in 2028,” per Aerospace America. NASA has not said which lander will fly Artemis IV.
A NASA article published Nov. 4 summarizes the same Oct. 23 update. It describes Artemis III as a 2027 test flight, not a lunar mission, and says SpaceX and Blue Origin are both targeting a crewed landing in 2028. Isaacman’s line there was that “this is a very energized NASA, and these updates are only a small part of that story.”
The year-end test and the unfinished hardware
The nearest milestone is a year-end tanking test. Isaacman described the path to a “year-end tanking test and summer 2027 Artemis III launch,” Aerospace America reported, and a chart at the briefing showed a launch window of May to September 2027.
The government-built hardware is further along. The mission page says NASA moved the SLS core stage from the Michoud Assembly Facility to the Pegasus barge on April 20, 2026, bound for Kennedy Space Center in Florida for final outfitting and integration, and a headline on the same page says the core stage joined its boosters at Kennedy on Oct. 28. Aerospace America had reported the plan to integrate the solid rocket boosters with the core stage in October, so the rocket for Artemis III is already stacking while the landers it will meet are still being built and tested.
Both lander teams had work to do. Blue Origin was rebuilding its launch complex after a New Glenn explosion on the pad in May, and aimed to resume pad operations in November. SpaceX was analyzing data from its recent Starship flight, the first time that design reached orbit, and building the passive docking system for Artemis III, with a Starship flight targeted for November.
SpacePolicyOnline adds that SpaceX plans an in-space propellant transfer early next year and an uncrewed lunar landing test in late 2027, while Blue Origin dropped propellant transfer in favor of three Blue Moon Mark 1 spacecraft acting as tugs. NASA’s Aerospace Safety Advisory Panel, it reported, questioned lander readiness, the single uncrewed test planned for each provider and the first use of cryogenic propellants on the Moon.
In a September note to the workforce, Isaacman called the mid-2027 date “90 days broken to schedule,” SpacePolicyOnline reported, and he later said the message was meant to motivate staff. Whether the year-end tanking test lands on time is the first public check on that date.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Arizona’s governor declared a statewide emergency after Flagstaff logged its wettest Nov. 1 on record
- Zero Motorcycles unveiled an electric motorcycle targeted at under $8K and a street-legal dirt bike at EICMA
- New FCC rules on how people can stop robocalls and texts take effect Nov. 25
- Neanderthals in Spain carved a wooden object that matches nothing archaeologists have ever found