West Virginia approved a $2.48 billion gas plant that ratepayer advocates fought

Next to a coal plant that has burned since 1968 in Monongalia County, West Virginia’s two FirstEnergy utilities now have permission to build something new. The state Public Service Commission has approved a $2.48 billion, 1.2-gigawatt natural gas power plant in Maidsville as part of a $2.7 billion plan that also adds 70 megawatts of solar, over the objections of consumer advocates and environmental groups.

Read next on Morning Overview: A Swiss mountain pass that melting ice keeps opening up has given up a 4,000-year-old bronze neck ring

The opponents’ main worry is who carries the risk. The commission agreed to let the utilities start charging customers for construction years before the plant produces any power, to serve a data center whose demand has not yet arrived.

A 1.2-gigawatt plant and a monthly construction surcharge

In its November 17 decision, the commission approved the plan by Monongahela Power and Potomac Edison and allowed them to recover construction and financing costs through a monthly surcharge, Utility Dive reported. The surcharge is expected to raise residential bills by $1.18 a month, or 0.9%, at first. It will be recalculated every six months based on actual construction spending and will run until the assets enter base rates after the gas plant comes online, expected in late 2031. The combined-cycle gas plant itself, called the Maidsville Energy Center, is expected to cost $2.48 billion.

The utilities chose the site in February, a 35-acre parcel beside their Fort Martin Power Station. FirstEnergy said in its announcement of the Maidsville site that the plant would generate enough energy to power roughly half a million homes and that site work could begin as early as 2027. Fort Martin, one of West Virginia’s oldest coal-fired plants, has operated since 1968, West Virginia Public Broadcasting reported when the application was filed.

The gas plant does not replace coal, and it is not a stand-alone bet on gas. The utilities’ integrated resource plan also calls for continued operation of the Fort Martin and Harrison coal plants, rated at 1.1 gigawatts and 2 gigawatts, alongside new solar, including the 70 megawatts approved in this case, according to Enerdata’s summary of the proposal.

Consumer bills are the most visible piece of the decision. The initial $1.18 monthly increase is modest, but because the surcharge is recalculated twice a year on actual construction-work-in-progress balances, it will rise as spending ramps up. Residential customers will see that line item for years before the plant sends a single kilowatt-hour to the grid, which is the core of the advocates’ complaint that the arrangement shifts project risk from the utilities to ratepayers.

Built for a data center that is not yet plugged in

The driver is a single large customer. Commission staff said the project was prompted by an unnamed data center that would need 100 megawatts of capacity in 2028, rising step by step to 1,012 megawatts by 2033. A commission analysis found Mon Power projected a summer peak of 2,997 megawatts in 2026 and could face a 60-megawatt capacity shortfall in 2028, growing to 2,194 megawatts in 2034 as data centers and other large loads are added. That gap comes as capacity prices in the PJM Interconnection, the regional grid operator, have surged in recent years, the commission noted.

Intervenors argued the forecast may never materialize. The Sierra Club said the utility’s $4 billion rate base would grow by 67% because of the project and urged Mon Power to adopt large-load tariffs so the customers driving the upgrades pay for them. Anna Sommer, a principal at Energy Futures Group who testified for the West Virginia Citizen Action Group, Solar United Neighbors and Energy Efficient West Virginia, questioned the plant’s levelized cost of energy. “The underdevelopment of the Companies’ CC proposal introduces significant risk of cost increases and schedule delays,” she wrote.

What happens if the plant is never finished

The commission defended the surcharge by pointing to precedent. It noted the mechanism had been used before, including for Pepco Holdings’ canceled Mid-Atlantic Power Pathway transmission project, which was ultimately allowed to recover more than $80 million from ratepayers despite never being completed. Mon Power argued that the surcharge would prevent a credit downgrade by keeping cash flowing during construction.

The order also anticipates trouble. In the “unlikely event that construction ceases or experiences extraordinary delays,” the commission said it will “initiate an appropriate proceeding to determine the applicable accounting and ratemaking treatment, surcharge or base rate recovery and the timing of such recovery.”

The timeline is long. The utilities said in February that they expected a decision within a year, and Power Engineering reported that the plant was designed to come online in late 2031. That leaves roughly five years in which West Virginia customers will pay the surcharge while the data center load that justified the project either shows up or does not.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.