TVA will collect $1.7 billion from one data center customer under a new tariff

The federal utility that supplies power across the Tennessee Valley has put a price tag on what one big data center is worth to it. The Tennessee Valley Authority says it is set to receive $1.7 billion in aggregate payments from a single, unnamed data center customer under a new tariff aimed at large computing loads.

Read next on Morning Overview: Ukraine says drones hit a Kalibr missile ship in Russia’s Baltic Fleet

The deal is the first concrete look at how TVA’s new pricing for data centers translates into revenue. It arrives as the federal utility reports record demand, rising data center sales and its biggest capital spending program ever.

About $1.5 million per megawatt of requested capacity

TVA disclosed the agreement in a Nov. 12 filing with the U.S. Securities and Exchange Commission, according to Utility Dive. The new tariff applies to data centers larger than 5 megawatts.

“Capacity commitment charges under the agreement are based on a rate of approximately $1.5 million per MW of requested capacity above 5 MW,” the filing said. “This rate reflects TVA’s current cohort-based pricing methodology, which may be revised for future customer cohorts.” In other words, data centers are grouped and priced in batches, and later groups may pay a different rate.

The tariff took effect Oct. 1 and will be phased in through 2029, the filing said. Utility Dive, citing reporting by the Nashville Scene in August, said the phase-in lets existing customers keep their current rate structure for a period of time.

TVA did not name the customer. As a federal corporation, the utility publishes annual and quarterly reports through the SEC’s EDGAR system, which is where the agreement first surfaced.

Data centers lift sales and profits

TVA CEO Mike Skaggs said during a Nov. 13 earnings call that the change in data center rates has supported the utility’s investments, including extending the lives of its existing nuclear units and “helping expand the nuclear fuel and supply hub in the East Tennessee area.” The utility’s board made Skaggs, who had come out of retirement to serve as interim CEO, the permanent chief executive at a Nov. 10 meeting.

The utility’s fiscal 2026 results, which TVA outlined in an investor press release, show how much data centers already matter. According to a summary by the American Public Power Association, TVA reported $14.2 billion in total operating revenue on nearly 172 billion kilowatt-hours of sales for the fiscal year that ended Sept. 30, an increase of about 4 percent. Electricity sales rose about 2 percent, driven primarily by higher sales to the data processing, web hosting and related services sector, along with residential and small commercial customers and a 10 percent increase in cooling degree days.

Net income reached $2.1 billion, up $761 million from the prior year, mainly because of higher revenue and lower operating expenses. Operating and maintenance costs fell $264 million, largely because of Inflation Reduction Act tax credits, while fuel and purchased power costs rose $329 million because of higher market prices and natural gas costs.

Gas, nuclear and a $13 billion spending plan

TVA president and chief financial officer Tom Rice said the utility is in a “strong financial position” to carry out a $13 billion capital investment plan over the next three years, on top of more than $23 billion invested since 2020, Utility Dive reported. The full remarks are in the investor webcast transcript.

Part of that money is going to new natural gas generation. TVA’s board approved 1.5 gigawatts of new gas capacity in August, targeted to come online in 2032. As of Sept. 30, TVA had spent $463 million on long-lead equipment from a previously approved project that will now be used for the new plant, and it could spend up to an additional $3.1 billion. That earlier effort, the Middle Tennessee Energy Solution project, has been folded into what TVA calls New Gas Facility 2032.

On nuclear, TVA recently received the first construction permit the Nuclear Regulatory Commission has issued for a small modular reactor, a BWRX-300 design at the Clinch River Site in Oak Ridge, Tennessee. TVA’s filing cautioned, however, that it “has not yet decided whether to construct a reactor at the site.”

Cost pressures and rates

The filing also warned of headwinds. TVA said it “continues to experience supply chain pressures resulting from inflation, tariffs and other trade restrictions, material constraints, and labor availability,” which have contributed to project delays, limited access to critical materials and higher costs.

TVA expects inflationary and tariff pressures to persist into 2027. While those challenges have so far been managed with limited disruption, the utility said, continued or escalating pressure could lead to more substantial operational impacts “and increased pressure on power rates.”

In its fiscal 2026 statement, Rice said continued financial strength is central to investing in existing assets, building new generation and transmission and reliably serving the region’s growing energy needs while keeping rates low for customers.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.


More from Morning Overview

Morning Overview is reader-supported. Some links in our articles are affiliate links, and we may earn a commission at no extra cost to you. As an Amazon Associate I earn from qualifying purchases. Full disclosure.