Data centers could wait half as long to plug into PJM’s grid under a new plan

A developer who wants to connect a data center campus to the largest grid in the country currently faces a queue measured in years, with separate studies for the power plant, the transmission upgrades and the customer. On Nov. 16, 2026, PJM Interconnection asked federal regulators to replace that sequence with one annual cycle that the grid operator says would take about half as long as today’s process.

Read next on Morning Overview: A Cirrus SR22 declared an emergency a minute after departure clearance, its parachute still bagged

Data center demand is the reason FERC ordered every major grid operator to explain how such customers connect. PJM’s proposal, called the Fast Energization Process, is still only a proposal: the Federal Energy Regulatory Commission has not ruled on it.

One 12-month cycle in place of three tracks

PJM’s filing, as reported by Utility Dive on Nov. 17, would study large-load and generation requests together in a single, one-year process. PJM says the approach is about twice as fast as the current process. Utility Dive gives no length for the existing cycle, so “half as long” is PJM’s own characterization.

PJM’s slides to its Members Committee show where the time goes today. A transmission owner’s load interconnection review takes roughly two to three months “or longer,” a separate study takes six to seven months, and transmission approval and construction can add up to 12 more months. Generation requests take about two years from application to agreement. The Nov. 5 presentation replaces those with a four-month screening window, a system impact study of roughly six months and about a month to finalize agreements.

Donald Bielak, PJM’s director of interconnection planning, told FERC the proposal is “the next evolution of PJM’s interconnection process and further enhancement to the currently effective Cycle process.”

PJM told FERC what is wrong with the current setup, according to Utility Dive: “insufficiently fast interconnection processes for load and generation,” parallel and duplicative studies, speculative requests, limited visibility into what drives transmission upgrades, and a resource adequacy shortfall. Merging the queues is its answer to the first three.

Gates, deposits and cost recovery

Speed comes with strings. PJM’s Oct. 28 presentation to the Markets and Reliability Committee says projects are withdrawn at the gate if they lack an initial readiness deposit, verified site control, a verified permit matrix, verified technical data or transmission owner approval, including a signed cost recovery agreement for large loads. The principle stated there is to preserve “the first-ready, first-served paradigm.”

Money is the other string. Reporting by Power magazine says the process would move PJM away from tying specific upgrades to specific projects, toward a portfolio of reliability reinforcements, with a 14-week early engagement period and tighter readiness deposits. Transmission owners propose assigning reinforcement costs to zones with large-load requests for 15 years before standard allocation applies. Customers would sign cost recovery agreements with minimum revenue commitments of 80 to 100 percent of firm-service revenue.

PJM’s own slides list estimated large-load security of $5,000 per megawatt at the first decision point and $8,000 per megawatt at the second, and say the figures are estimates.

Why FERC asked in the first place

PJM filed a second piece the same day: ride-through rules for large computational loads. Under the Oct. 28 slides, the rules apply to loads of 50 megawatts or more with at least 25 megawatts served by power electronic equipment, with the goal of preventing large block load loss during voltage and frequency disturbances. New projects would be covered from Jan. 16, 2027, and existing loads must comply by the later of Jan. 16, 2028 or one year after their commercial operation date.

The filings answer show-cause orders FERC issued on June 18, 2026 to each of the six regional grid operators it regulates. According to law firm Orrick’s summary, FERC preliminarily found that existing rules “may be unjust, unreasonable or unduly discriminatory or preferential,” and proposed treating a large load as a customer of at least 50 megawatts of peak demand at one site.

Commissioner Chang cautioned that “reliance on bilaterally-negotiated agreements may not be sufficient to protect customers against unjust cost shifts.”

PJM was not alone. ISO New England filed on Nov. 13 and would require large loads to bring their own new capacity. The Midcontinent Independent System Operator called its proposals “an important milestone, not an endpoint.” Power magazine lists filings from the California, New York and Southwest Power Pool operators as well, the last of them on Nov. 20.

What still has to happen

Power magazine reports that most of PJM’s transmission service revisions are proposed to take effect on March 16, 2027, while the Fast Energization Process itself is expected in late November 2027. A data center developer filing today would therefore see no change from the one-year cycle for roughly a year, assuming FERC approves it as filed.

The unanswered question is how regulators weigh speed against who bears the upgrade bills. FERC’s decision on the PJM filing will show whether the 15-year zonal assignment and the 80-to-100 percent revenue commitments survive the comment period.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.