Utilities that order a large power transformer today are told to plan for a wait of two years or more, and the price of some units has multiplied several times over in five years. On Oct. 30, 2026, the Energy Department put a dollar figure on its response: $237 million in grant money, announced as “over $230 million,” aimed at easing the grid transformer shortage by getting old equipment back into service and making more of the parts at home.
Read next on Morning Overview: Refiners are making less gasoline and more diesel, and here’s why
The money has not been awarded. It is a funding opportunity, with applications still to come, and the department’s own page names no winners yet.
Two pots of money, $50 million and $187 million
The opportunity is called Grid SCALED, short for Grid Supply Chain Alternatives to Lead Energy Dominance, and it is the first funding opportunity under the department’s Grid Supply Chain Program, which is authorized for up to $375 million, according to the Energy Department’s announcement.
Topic area one sets aside up to $50 million for projects that expand refurbishment and reuse of existing grid equipment. Topic area two offers up to $187 million for projects that scale up alternative materials and subcomponents sourced and made in the United States.
The department estimates the combined effort would save utilities about $125 million a year and keep roughly $50 million a year in the U.S. economy that would otherwise go to foreign suppliers. Both figures are the department’s projections, not results, and the announcement does not say how many transformers the program would put into service.
Who can apply and how big the awards are
A summary of the formal notice of funding opportunity by law firm Holland & Knight lays out the mechanics. The Office of Electricity issued the notice on Oct. 30. Refurbishment awards are expected to run from $2.5 million to $15 million, for 3 to 20 projects, open to utilities and refurbishment facilities that reclaim, repair and recertify retired equipment. Both topic areas require at least 50 percent cost share.
The alternative materials area is aimed at U.S. suppliers and manufacturers scaling domestically sourced products at technology readiness level 6 or higher, such as electrical steel, ceramic bushings and copper windings. Awards range from $1 million to $25 million, for 7 to 50 projects. Work would run in two stages, up to 12 months of manufacturing readiness and supply chain formation, then up to 36 months of production scale-up that depends on a go or no-go review. Applicants need a letter of commitment from an upstream supplier.
The shortage the money is meant to address
The department’s Office of Electricity describes the problem in an August 2026 page on the U.S. grid supply chain. After nearly 20 years of flat electricity demand, load growth has run close to 3 percent a year since 2023, driven by data centers, manufacturing and general growth. Lead times for critical equipment, it says, are two or more years, and some transformers have seen price increases of 4 to 9 times over the past five years, costs that utilities pass to customers.
It names reliance on imported parts and materials, limited domestic production capacity and excessive customization as root causes, and projects up to a 10 percent cut in imports and lead times and up to a 25 percent cut in utility spending on essential equipment from its supply chain program.
Energy Secretary Chris Wright said the department is investing in American-made technologies and modernizing the grid. Katie Jereza, the assistant secretary for the Office of Electricity, said: “America should never have to rely on foreign suppliers to keep the lights on.”
The cost pressure reaches household bills. T&D World, citing J.D. Power, reports average monthly residential utility bills of $409 in the third quarter of 2026, up 2.8 percent on an annualized basis from the third quarter of 2025. The electricity portion was $188, up 5.6 percent from $178 a year earlier. The article does not link those bills to transformer prices; the department’s argument is that cheaper, more available equipment lowers what utilities must recover from customers.
Deadlines and what comes next
The required concept papers were due Nov. 20, 2026, so the window to enter has already closed for new applicants; only those that submitted one can file a full application, due Feb. 8, 2027, according to the department. The formal notice anticipates selection notifications around June 25, 2027 and awards around Sept. 23, 2027, as summarized by Holland & Knight. Those dates are targets and may move.
The Grid SCALED call is also not the end of the program. The trade group publication American Public Power Association’s news service reports that further announcements are expected in 2027, including for solid-state transformers and common configurations meant to streamline manufacturing. T&D World adds that those technologies are cited as beneficiaries of a stronger domestic supply chain.
What remains open is whether $237 million moves the needle against a gap measured in years. With awards not expected until September 2027, the first real test is which companies the department picks and how fast their output reaches utilities.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- A flight school faces a $2,388,500 FAA fine for flying an unairworthy plane
- Hidden wear was found inside a New Jersey nuclear reactor during its outage
- Operational F-15EX jets now fly with extra fuel tanks the Air Force never planned for
- A Cirrus SR22 declared an emergency a minute after departure clearance, its parachute still bagged