The grid that keeps lights on across 13 states and Washington, D.C., expects to break its own winter record this season. PJM Interconnection, the largest power grid in America, says the peak demand it is planning for is about 147,500 megawatts, and the fastest-growing source of new load is data centers.
Read next on Morning Overview: Toyota is sweetening its 375-horsepower bZ Woodland electric SUV with 0% financing
A peak of that size would top the 143,700 megawatts PJM served on Jan. 22, 2025. It arrives with a thinner cushion than operators once had, and with an emergency tool that has been used more in the past two years than in the previous eight combined.
A forecast above the old record
PJM released its winter outlook on Nov. 5, 2026. The outlook puts expected peak demand at about 147,500 MW, plus an average of roughly 3,200 MW in exports to neighboring systems, against about 182,426 MW of operational capacity. If the peak arrives, it would be a new winter high.
The prior winter’s forecast was already near the record. A year earlier, PJM’s winter outlook of Nov. 3, 2025 forecast about 145,700 MW and noted the all-time winter high of 143,700 MW. PJM said its reserve margin at the January 2025 peak was 8,700 MW, compared with a forecast 7,500 MW margin for winter 2025-26. Aftab Khan, PJM’s executive vice president for operations, planning and security, said then that shrinking margins could begin affecting operations within a few years if the trend continues.
Stress cases go higher. PJM’s studies cover customer demand of up to 152,200 MW, and the grid operator says its Pre-Emergency and Emergency Demand Response programs can maintain reliability in those cases, according to the American Public Power Association’s summary of the outlook.
Data centers and the extra load
Forecast winter peak demand has risen about 7,500 MW, or 5%, since 2022, and data centers and other large-load customers are a major driver, PJM says. In an Oct. 15, 2026 post, David Souder, PJM’s executive director of system operations, wrote that “Most of the new, rapidly growing energy demand is from data centers and other energy-intensive Large Load customers.” He added that the “expanding demand is outpacing new transmission and electricity supply coming onto the system.”
Such customers behave differently from a cold snap. Souder’s post said their usage stays steady year-round and does not track seasonal weather, and that about 11,000 MW of data center load is already on the system. A winter peak driven by heating now sits on top of a floor that no longer drops in the shoulder months.
Souder described the squeeze as rising energy flow on the transmission system while generation reserves dwindle. The same PJM post reported more than 61,000 MW of generation out of service during the week it was written, mostly planned maintenance, with about 15,000 MW of preliminary unplanned outages, and said PJM recalled about 10,000 MW to service.
Demand response and the backup-generator order
PJM has leaned on customers to cut use. According to the outlook, demand response, in which customers are paid in advance to reduce power on request, was activated 15 times across 2025 and 2026, compared with eight times in the previous eight years.
The U.S. Department of Energy has also given PJM emergency authority to direct data centers and other large loads to run their backup generators as a last resort. PJM says it has never used that authority. The operator also plans to ask DOE for orders that let designated generators exceed permitted emission levels during emergencies.
Michael Bryson, PJM’s senior vice president of operations, said the grid operator will “proactively manage the system to perform at high levels when consumers need energy the most.” Souder put the burden on power plants in the outlook statement, saying generator performance is “more critical than ever” given how little room for error remains.
The tool is also in regular use outside winter. In the Oct. 15 post, PJM said demand response was activated on nine days in 2026, including Oct. 13 and 14, and that DOE had issued its ninth order of the year allowing PJM to direct data center backup generation. Those orders are standing permissions, not deployments.
The Winter Storm Elliott yardstick
The risk PJM names is plant outages as much as demand. The outlook says generator outages on the scale of Winter Storm Elliott, about 46,000 MW, could leave the system exposed to power outages. Winter Storm Fern in early 2026 was the longest stretch of extreme cold PJM has seen since the 1990s, with hourly peaks above 130,000 MW for eight days from Jan. 26 to Feb. 2.
To cut that exposure, PJM’s cold-weather site visit program with ReliabilityFirst is in its fourth year, and Power Engineering reported on Nov. 9 that expected visits rose from fewer than 10 before 2023 to 30 to 35 this year. PJM says plants that hosted visits had lower outage rates than those that did not, and a similar program with SERC is starting for the rest of the footprint.
Constraints are local as well as regional. Power Engineering reported that strong generator performance matters most in the BGE, Pepco and Dominion zones, where transmission limits cap imports. The outlook’s own framing is conditional: “Reliable winter operations will depend on continued preparation and strong generator performance,” PJM said on Nov. 5. Whether 147,500 MW is reached depends on the weather in January and February, and the figures above are forecasts that PJM can revise.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Apple quietly pushed security fixes to nearly every iPhone, even ones stuck on iOS 18
- Expedia confirms hackers got in through a supplier, and here’s what to watch for
- A dangerous flash flood warning hit Broward County after an overnight deluge
- Florida’s St. Johns River just topped its worst flood on record near Cocoa