For the people of Covert Township, on the Lake Michigan shore, a reactor that went dark in 2022 may be producing power again within days. U.S. Energy Secretary Chris Wright, who toured Michigan’s Palisades nuclear plant on Oct. 29, said it may start up again as soon as the end of November. If it does, Palisades would be the first American reactor brought back after being shut down for good.
Read next on Morning Overview: A Cirrus SR22 declared an emergency a minute after departure clearance, its parachute still bagged
The timetable is still a target, not a schedule. Wright said the owner, Holtec International, has only a few tests and regulatory hurdles left, and the plant has slipped past earlier restart dates more than once. As of the sources reviewed on Nov. 24, no announcement of a startup had appeared.
What Wright said on the tour
Michigan Public reported that Wright, standing at the plant, said of the reactor: “it will be started in a few weeks.” The same report said he stressed careful, meticulous work on safety, and that a few tests and regulatory steps remain. Holtec’s spokesman told the outlet that after the Nuclear Regulatory Commission gives its go-ahead, operators will bring the reactor slowly from low power to full power over several weeks. The report did not say the NRC had yet cleared the restart.
A second account of the same visit, from WKZO, framed the timing more loosely, reporting that Wright expects the plant to be running by the end of 2026 while hoping for the end of November.
A fuel assembly that tipped in August
Holtec announced on Aug. 30 that fuel loading had begun, which put the plant in Mode 6 under its technical specifications. The core is to hold 204 fuel assemblies, a mix of new fuel and partially used fuel from recent operating cycles, and is designed for 805 megawatts of electricity. Chief Nuclear Officer Fadi Diya called the loading “an important milestone.”
The milestone was interrupted almost at once. After Aug. 30, one assembly tipped as new fuel was lowered into the reactor, and the restart was put on hold, The National reported on Oct. 16. The NRC said no radiation was released, and it allowed Holtec to retrieve the assembly under agency monitoring. Holtec said its recovery approach rested on engineering evaluations covering structural integrity, fuel handling, thermal conditions and radiation protection.
By Oct. 22, local station WWMT reported that Holtec said it had fixed the tilted assembly using a device the company built itself, which Holtec described as clearing a major obstacle. Michigan Public’s Oct. 29 report said fuel had been reloaded earlier in October after what it called an unexpected snag in August.
Safety culture questions from the NRC
The NRC’s own inspection raised a separate concern. According to The National, the agency wrote to Holtec that the plant had a safety-conscious work environment overall, but that a “chilled work environment” existed in the supply chain and quality assurance departments, where employees were hesitant to raise safety concerns for fear of retaliation. An NRC spokesperson said the agency found no violations or significant plant safety issues, and would keep verifying safety requirements. Holtec’s Patrick O’Brien said the company would work to strengthen the culture.
Critics have gone further. Kevin Kamps, executive director of the group Don’t Waste Michigan, told Michigan Public: “Once they restart this zombie reactor, all bets are off.” Holtec CEO Kris Singh has taken the opposite view, calling the restart a “nuclear renaissance” and saying the plant “will be better than a new plant and it will have another 50 years.”
Money, licenses and a missed date
The U.S. Department of Energy has offered up to $1.52 billion in loan guarantees to fund the restart, Michigan Public reported, and Gov. Gretchen Whitmer and state lawmakers have backed the project. The plant’s current operating license expires in 2031, so the 50-year claim depends on a later renewal. Holtec told the NRC in 2024 that it intends to seek a second license renewal that would extend operation to 2051, World Nuclear News noted in July.
The history of the schedule is part of the story. ANS Nuclear Newswire reported on July 8 that Holtec’s earlier target of reconnecting to the grid by the end of February 2026 had passed with no new date set, and that Singh told the Financial Times he expected a restart this year, ahead of a power supply contract that runs to March 2027. The National’s Oct. 16 report added that a source close to Holtec said the company hoped to be online by March 2027, though Holtec had published no official timeline.
Whether Palisades starts up by Nov. 30 now rests, as the Michigan Public account makes plain, on the NRC’s clearance and on Holtec’s remaining tests. Neither had been announced in the reports read through Nov. 24, and Wright’s “few weeks” remains the Energy Department’s estimate rather than a regulatory decision.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Up to 5 feet of snow is burying Donner Pass, and forecasters warn against Sierra travel
- A flight school faces a $2,388,500 FAA fine for flying an unairworthy plane
- Hidden wear was found inside a New Jersey nuclear reactor during its outage
- Operational F-15EX jets now fly with extra fuel tanks the Air Force never planned for