Some of the newest nuclear capacity on the U.S. grid may come from reactors built decades ago. Constellation Energy, the largest U.S. nuclear operator, told investors this month that it plans to squeeze 1,165 megawatts of additional capacity out of its existing plants through uprates, at an estimated cost of $4.3 billion.
Read next on Morning Overview: Arizona declared a statewide emergency after storms and floods battered homes and roads
An uprate involves no new site and no new reactor: it raises the output of a unit that already feeds the grid. Constellation laid out the plan in its third-quarter update, and the company’s chief executive, Joe Dominguez, said the work is not done: Constellation has “not finished exploring uprates at plants,” and “design and engineering work continues.”
1,165 megawatts and a $4.3 billion price
Nuclear Newswire, the American Nuclear Society’s news service, reported on Nov. 12 that Constellation signed agreements with three customers for 4,560 MW in the quarter, and that 1,165 MW of that is new nuclear capacity from ongoing and planned uprates. The company put the cost at $4.3 billion: about $1.3 billion in 2026 and 2027 and $3 billion from 2028 through 2032, according to that account.
The company’s own earnings release, issued Nov. 9 from Baltimore, frames the numbers differently. The release cites about 890 MW of incremental capacity from a power purchase agreement with Google across 11 nuclear units, plus a 190 MW expansion at Calvert Cliffs for Amazon, roughly 1,080 MW together, and says the Google deal will enable more than $4.3 billion of investment in Illinois, Pennsylvania and New Jersey, with the first uprate expected in 2028. The totals differ by the way each source counts, and the release does not state 1,165 MW.
A federal loan behind the uprates
Money is already lined up. On Oct. 27, the Department of Energy announced a conditional loan commitment of up to $5 billion for uprates at eight Constellation plants: Braidwood, Byron, Clinton, Dresden, LaSalle and Quad Cities in Illinois, Calvert Cliffs in Maryland and Limerick in Pennsylvania, according to the department’s announcement. DOE says the work would add nearly 1.1 gigawatts, enough for more than 930,000 homes, and support more than 10,000 project-related jobs.
The commitment is not final. Constellation has to meet technical, legal, environmental and financial conditions before DOE signs definitive documents and funds the loan.
Energy Secretary Chris Wright said the uprates would add 1.1 GW from 15 reactors at the eight plants, and described the output is “significantly more energy” that “puts downward pressure on rates,” as Nuclear Newswire reported. Constellation says the loan covers eligible costs from 2023 to 2035 and gives DOE an option to finance future uprates at other Constellation sites.
Customers are paying for much of the new output. Nuclear Newswire ties Calvert Cliffs to an Amazon agreement announced Oct. 1, a Google agreement spanning 11 units announced Oct. 6, Clinton to a 2025 Meta agreement and Dresden to a Walmart agreement. The uprates are tied to named buyers, and a share of the spending would be financed with federal credit.
What an uprate involves
The Nuclear Regulatory Commission sorts uprates into three kinds. Its backgrounder on power uprates says measurement-uncertainty uprates raise licensed power by less than 2 percent, stretch uprates are typically between 2 and 7 percent, and extended uprates “have been approved for increases as high as 20 percent,” usually after significant changes to major non-nuclear equipment.
Each needs an amendment to the plant’s operating license, with a 30-day public comment window and a 60-day window to request a hearing. As of January 2022, the NRC had approved 171 uprates, a gain of roughly 8,030 megawatts electric.
Crane, the restart that is ahead of plan
Constellation is also reopening a reactor instead of upgrading one. The Crane Clean Energy Center, the former Three Mile Island Unit 1, is on track to restart in the second half of 2027, which the company describes as ahead of schedule. Fuel assemblies and transformers are already on site, and the NRC issued a final environmental assessment and a finding of no significant impact in September, which Dominguez called “favorable.”
The existing fleet is running hard in the meantime. Constellation reported 46,677 gigawatt-hours of nuclear generation in the third quarter and a 97.2% capacity factor, excluding the partly owned Salem and South Texas Project plants.
Dominguez said the new product gives “customers another path to get new demand on line efficiently,” with pairing a customer with a battery storage provider as one example. The company signed its first Peak+ agreement, a 20-year, 270 MW deal for energy, capacity and nuclear attributes from its existing fleet starting in 2028; the customer was not disclosed. Which of the eight plants carries which share of the 1,165 MW, and how much the final DOE loan terms change the $4.3 billion, remain open in the filings read.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Ocean mud suggests Cascadia and the San Andreas fault have broken within hours of each other
- Monster waves battered California, flooding streets and closing piers along the coast
- Hackers broke into Japan’s Fugaku supercomputer and stole the SSH keys of its users
- Student pilots are stuck with nearly 60-year-old T-38 jets that work only half the time