A pool of water in central Texas has become the proving ground for Oklo’s plans to build a fleet of small reactors, and the company has just been told it can use that pool without restriction. The Department of Energy cleared the last operations hold point on Nov. 11 for Groves-1, the Groves Isotope Test Reactor, so Oklo won DOE approval to turn the reactor into an operating test platform for research, testing and training.
Read next on Morning Overview: Arizona declared a statewide emergency after storms and floods battered homes and roads
Groves-1 sits near Lockhart in Caldwell County, Texas. It first reached criticality in early August 2026, less than a year after groundbreaking, and the new approval moves it from a demonstration project to an operating facility.
What DOE cleared on Nov. 11
Oklo announced the clearance on Nov. 11, and World Nuclear News reported on Nov. 12 that DOE had cleared the final operations hold point, allowing unrestricted operation. The American Nuclear Society’s Oklo roundup describes the new status as an “operating platform for research, testing, and training.”
The reactor is a pool-type, water-cooled design. According to ANS, Oklo plans to use it to test capabilities for its future isotope reactors and its Aurora fast reactors, and operators wore eye-tracking glasses during a recent startup to help refine the human-machine interface. Neither the ANS roundup nor the World Nuclear News report gives a power rating for the unit.
Oklo co-founder and chief executive Jacob DeWitte called the achievement “an important demonstration,” saying that taking Groves-1 “from greenfield to criticality in less than a year” was the point, as quoted by World Nuclear News. Chimi Zacot, DOE’s acting deputy assistant secretary for nuclear reactors, said the department’s Reactor Pilot Program had “reset the nuclear industry’s expectations” for speed.
How Groves-1 reached this point
Groves-1 is one of the projects in DOE’s Reactor Pilot Program, which World Nuclear News says selected 11 advanced reactor projects in August 2025. DOE’s own announcement of the criticality said the reactor went critical the night before its Aug. 6 announcement and was the fifth DOE-authorized advanced reactor to do so this summer, following designs from Antares Nuclear, Valar Atomics, Deployable Energy and Aalo Atomics.
Assistant Secretary for Nuclear Energy Ted Garrish said in that announcement: “Oklo’s Groves Isotope Test Reactor is part of the revival of America’s nuclear energy industry.” DOE said the test reactor will inform a future commercial version that would produce isotopes for medicine, manufacturing, research, space and national security.
The Texas site has a distinction of its own. In the investor-wire copy of Oklo’s Nov. 11 announcement, Groves-1 is described as the first reactor in the Reactor Pilot Program to reach criticality on privately owned land, and the release says the DOE clearance lets the facility proceed with research, testing and personnel training.
The practical difference between the two milestones is in the paperwork. A first criticality in August showed the core could sustain a chain reaction at low power. The Nov. 11 clearance removes the final hold point, so Oklo can run the unit for the research and operator-training work it has described, without the restrictions that applied before.
Aurora-INL and the fuel contracts
Groves-1 is a stepping stone toward Aurora-INL, a 75-megawatt-electric liquid-metal-cooled fast reactor that Oklo is building at Idaho National Laboratory. Groundbreaking was in September 2025, and according to the ANS roundup, Oklo announced on X on Nov. 11 that structural concrete and steel were in place.
DOE’s Idaho Operations Office approved the project’s preliminary documented safety analysis in June 2026, according to ANS. The documented safety analysis is the step that remains before final authorization and operation, and Oklo has not announced progress on it. The PDSA followed a March 2026 other transaction agreement and a nuclear safety design agreement approved the same month, ANS reported, so the Idaho project has cleared a run of DOE steps in about three months. In its third-quarter update, the company said it plans to install major reactor components within the next 12 months and to begin building Groves-2 Forge in the same window.
Fuel is the other thread. Oklo signed what ANS describes as “multiple definitive, multiyear contracts” with Centrus Energy for high-assay low-enriched uranium, formalizing a June 2026 letter of intent. Oklo will make prepayments to support new enrichment capacity at Centrus’s American Centrifuge plant in Ohio, with deliveries scheduled to begin in 2029. Contract values were not disclosed, and ANS does not say how large the prepayments are.
The fuel is earmarked for a planned 1.2-gigawatt Oklo plant in Ohio, for refueling Aurora-INL and for later Aurora deployments. A separate agreement with U.S. Forged Rings, also covered in the roundup, reserves 27 Aurora module-equivalents of components across 2030 to 2035, with initial deliveries expected in 2030.
The open question is timing: DOE still has to sign off on Aurora-INL’s documented safety analysis and a final readiness review before the 75-megawatt reactor can start, and Oklo’s own update points only to the next 12 months for major components.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- USS Colorado will be the first U.S. submarine in AUKUS’s new Australian rotation
- Monster waves battered California, flooding streets and closing piers along the coast
- Hackers broke into Japan’s Fugaku supercomputer and stole the SSH keys of its users
- Student pilots are stuck with nearly 60-year-old T-38 jets that work only half the time