China’s Tianwan is one reactor away from becoming the world’s biggest nuclear plant

On China’s east coast, in Jiangsu Province, the last piece of what will become the largest nuclear power plant on Earth is nearly ready to start. Hot tests are finished at Tianwan unit 8, and its first load of nuclear fuel has arrived from Russia.

Read next on Morning Overview: Older Teslas mostly keep their batteries, and here’s what wears out instead

When unit 8 joins the seven reactors already built at the site, Tianwan will have about 9.1 gigawatts of installed capacity. That will push it past Japan’s Kashiwazaki-Kariwa, the current record holder, and into the top 10 of all power plants of any kind worldwide.

Hot tests done and Russian fuel delivered for unit 8

China National Nuclear Power, a subsidiary of China National Nuclear Corporation (CNNC), announced that it completed hot tests at unit 8 on Wednesday, November 25, World Nuclear News reported. Those tests simulate the temperatures and pressures the reactor systems will face in normal operation and check that equipment on both the nuclear and conventional sides of the plant meets design requirements. At the same time, Rosatom’s fuel division, TVEL, delivered the initial core load plus a reserve batch of fuel assemblies, made at the Novosibirsk Chemical Concentrates Plant.

Anton Ivanov, TVEL’s vice president for commerce and international business, said the past year had brought a record volume of nuclear fuel supplied to a single country. Since late 2025, he said, TVEL has delivered three complete VVER-1200 core loads, for units 7 and 8 at Tianwan and for unit 3 at Xudapu, another Russian-designed project in China. He added that the initial load for Xudapu unit 4 would be manufactured and accepted by the end of 2026.

Unit 8 has moved quickly through commissioning. CNNC said in August that cold functional tests, which check the leak-tightness of the primary circuit, marked the unit’s full transition from installation to commissioning. Fuel loading is the next major step, followed by first criticality and grid connection.

The schedule for unit 8 mirrors the path unit 7 took about a year earlier. CNNC announced in January that hot tests at unit 7 had been completed on December 30, 2025, and said then that the unit was expected to enter commercial operation within the year. Unit 7 went on to load fuel, reach criticality and connect to the grid in 2026, so a similar pace would put unit 8 on the grid sometime in 2027, in line with its scheduled commercial operation date.

Unit 7 already feeding the grid

Its twin is further along. Tianwan unit 7 delivered its first electricity on October 8, just over a week after reaching a self-sustaining chain reaction, according to World Nuclear News’ report on the grid connection. CNNC said all parties had “maintained a rigorous and meticulous work attitude” through steps including reactor criticality, turbine start-up and a generator short-circuit test. Rosatom said all systems operated in their standard design mode, Interfax reported, and described a power start-up that raises output in stages from 1% to 50% before a long build-up to full power, commercial operation and a two-year warranty period.

Units 7 and 8 both use Russia’s VVER-1200 design, each rated at about 1.2 gigawatts, under agreements Russia and China signed in June 2018. Construction of unit 7 began in May 2021 and unit 8 in February 2022. Unit 7 is expected to enter commercial operation later in 2026 and unit 8 in 2027, Enerdata reported.

Eight reactors, three designs and one record

Tianwan has been growing for nearly two decades. Its first four units, Gidropress VVER reactors supplied by Russia, entered commercial operation between June 2007 and December 2018. Units 5 and 6 use China’s own ACPR1000 design. The plant is owned and operated by Jiangsu Nuclear Power Company, a joint venture of CNNC with 50%, China Power Investment Corporation with 30% and Jiangsu Guoxin Group with 20%.

Once all eight units run, CNNC expects annual output of more than 70 terawatt-hours and a cut in carbon dioxide emissions of 57.4 million tonnes a year, according to World Nuclear News. For comparison, the current largest nuclear plant by operable capacity, Kashiwazaki-Kariwa, has seven units totaling 8.2 gigawatts.

Being in the top 10 of all power plants of any kind is a notable distinction for a nuclear station. The biggest generating sites in the world have traditionally been giant hydroelectric dams and coal complexes, and a 9.1-gigawatt nuclear plant would sit in that company on the strength of eight reactors on a single stretch of coastline.

The record would also say something about where nuclear construction is happening. A Russian-Chinese project on the Jiangsu coast is about to overtake a Japanese site, while the reactors driving the milestone come from Rosatom, which has kept supplying fuel to China at record pace. The remaining steps for unit 8, fuel loading, first criticality and grid connection, will decide how soon in 2027 Tianwan can claim the record.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.


More from Morning Overview

Morning Overview is reader-supported. Some links in our articles are affiliate links, and we may earn a commission at no extra cost to you. As an Amazon Associate I earn from qualifying purchases. Full disclosure.