A basemat 35 metres below ground, a tunnel boring machine assembled and ready, and a first turbine-building pour finished: the construction site at Ontario’s Darlington station looks like a project that is moving. Yet the unit going up there, the small nuclear reactor leading North America’s field, is behind schedule and over budget: Ontario Power Generation said in its third-quarter results on Nov. 10 that it will start late and cost more than planned.
Read next on Morning Overview: The EPA killed the credit behind the start-stop feature it calls almost universally hated
The first of four GE Vernova Hitachi BWRX-300 units is no longer expected to begin commercial operation by its October 2030 target, and it will not stay within its C$7.7 billion budget. Because every other small modular reactor project in the West is watching the same design, the slip carries weight well beyond Clarington, Ontario.
What OPG disclosed on Nov. 10
World Nuclear News, summarizing OPG’s results, reported that Unit 1 will miss the October 2030 date and exceed the C$7.7 billion (about US$5.4 billion) estimate, a figure that includes systems and services common to all the planned units at the site. OPG blamed ongoing engineering work by GE Vernova Hitachi Nuclear Energy on its first-of-a-kind reactor, which it said affects construction and supply chain performance. World Nuclear News carried the full account on Nov. 11. Separately, ANS noted that Q3 work included assembling the tunnel boring machine, with tunnelling for the condenser cooling water tunnel set to start in the last quarter of the year, and completing the first turbine building pour.
OPG has not yet set a new date or a new number. It expects to substantially complete a fresh cost and schedule assessment by mid-2027, covering engineering maturity, design complexity, inflation and geopolitical risk.
OPG President and CEO Nicolle Butcher said, as ANS Nuclear Newswire reported, that OPG has “identified risks that will impact Unit 1’s schedule and budget.” Butcher added that OPG will share information transparently as the work progresses, and the company is working with GE Vernova Hitachi to finish the outstanding engineering.
From 2028 to “late”: the schedule slide
Canary Media’s Dan McCarthy, in a Nov. 11 report, noted that when the design was announced in late 2021, OPG said completion could come as early as 2028. The target later settled at October 2030, and now that date has been dropped as well.
The money was set out earlier. In spring 2025, Ontario approved a C$20.9 billion budget for four BWRX-300 units. Canary Media says that figure covers all four reactors, which add up to roughly 1,200 megawatts at about 300 megawatts apiece. According to a Nov. 17 account in a Saskatchewan paper, the first unit was pegged at C$7.7 billion, including C$1.6 billion in common infrastructure, which left C$4.4 billion for each of the three follow-on units. Canary Media’s report gave no revised total for the four units and no new figure for Unit 1. The Canadian Nuclear Safety Commission issued OPG a licence to construct the first unit in April 2025, World Nuclear News noted, and long-lead items such as the reactor pressure vessel have already been procured.
A design that has never been built anywhere else
OPG’s explanation is the design itself. Engineering on the first-of-a-kind reactor is still being finished while construction proceeds, which the company says affects construction and its supply chain. GE Vernova Hitachi’s spokesperson, Jonathan Allen, told The Globe and Mail, as quoted by World Nuclear News, that “while engineering and design maturity are important considerations,” several interconnected factors across engineering, procurement and construction, along with inflation and geopolitical risk, also contribute.
Canary Media reported that only two small modular reactor plants operate commercially anywhere, one in Russia and one in China. It also pointed to the large reactors at Vogtle in Georgia, where units 3 and 4 came online in 2023 and 2024 after running about seven years late and $17 billion over. The second Vogtle unit was reportedly about 30 percent cheaper to build than the first, the report said, which is the learning-curve argument OPG’s later units depend on. The Tennessee Valley Authority received an NRC construction permit for a BWRX-300 at Clinch River in September, and Blue Energy has begun the NRC application process for one in Texas, Canary Media added. Those projects share the design Darlington is now proving.
Saskatchewan is already adjusting
The knock-on effects are showing up. SaskPower chose the BWRX-300 in 2022 in part because OPG would build it first, so Saskatchewan could learn from Ontario’s experience. On an Oct. 16 podcast, Jeremy Harrison, the minister responsible for SaskPower, said the multi-year Darlington delays mean the province cannot decide on its original timeline, and that it needs cost certainty before comparing a small unit with large-scale nuclear, the paper reported.
OPG’s own project page still describes Unit 1 as a 300-megawatt reactor in a four-unit plan with only the first unit’s licence application under review. Whether the mid-2027 reassessment lands near C$7.7 billion or well above it is the figure that every buyer of this design is waiting for.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- El Niño has hit +2.5°C, and a strong-to-very-strong winter event now looks likely
- The biggest grid drop in PJM history came from data centers, and now they may have to pay
- Back-to-back California quakes, and what the USGS says about the risk of a bigger one
- Toyota is sweetening its 375-horsepower bZ Woodland electric SUV with 0% financing