On the Texas Gulf Coast, in Calhoun County, a Dow chemical complex now holds a federal permit to build its own nuclear plant. The U.S. Nuclear Regulatory Commission issued the construction permit on Nov. 9 for the Long Mott Generating Station at Dow’s Seadrift Operations, covering four X-energy Xe-100 reactors.
Read next on Morning Overview: Toyota is sweetening its 375-horsepower bZ Woodland electric SUV with 0% financing
It is the first permit of its kind for a reactor on an industrial site, and the first for a high-temperature gas-cooled design in nearly 60 years. A permit to build is not a decision to build, though, and Dow has said it has not made one.
Four pebble-bed reactors for one chemical site
According to NRC news release 26-083, the permit went to Long Mott Energy, a Dow subsidiary, for a four-reactor facility whose units would mainly make high-temperature steam for the Seadrift site, with surplus electricity going to the grid. The agency described the approval as the first for a multimodule advanced reactor facility, the first for a pebble-bed core and the first for a design that refuels while running.
The technical details come from ANS Nuclear Newswire’s Nov. 10 report. Each Xe-100 produces 80 megawatts of electricity and 200 megawatts of thermal energy, for 320 megawatts electric across the four. The reactors are helium-cooled and fueled with TRISO particles made from high-assay, low-enriched uranium, and they are expected to run for 60 years. ANS adds that the Xe-100 can be deployed in configurations of four to 12 units, so Seadrift would use the smallest standard grouping. Dow expects Long Mott to be the first advanced nuclear project deployed at an industrial site in North America, according to its release. Seadrift’s interest is practical. Dow’s own announcement says the plant would supply zero-carbon electricity and steam to replace energy and steam assets that are nearing the end of their lives.
A review that beat its own clock
The application that started the clock was substantial. Under the NRC’s May 2025 notice, it included a preliminary safety analysis report and an environmental report, and it proposed four units at Seadrift using X-energy’s Xe-100 design, each producing about 80 megawatts of electricity and also supplying heat to improve the efficiency of Dow’s plant.
The NRC accepted the application for review on May 13, 2025, after the company submitted it on March 31 of that year. The finding of no significant impact on the environment followed in spring 2026, and the safety evaluation was finished in October, a month ahead of schedule, the NRC said.
NRC Chairman Ho Nieh framed the outcome as proof of a faster process. Nieh said in the release that the agency “delivered on the 18-month schedule,” and ANS quotes him adding that the result shows rigorous safety reviews can run on predictable timelines. The release also states that this is the third advanced reactor construction permit the agency has issued in 2026. ANS lists the other two as TerraPower’s Natrium plant in March and the Tennessee Valley Authority’s Clinch River BWRX-300 in September. X-energy chief executive Clay Sell, quoted by ANS, said that “getting the construction permit earlier than expected is reflective of the thorough and efficient work of the NRC.”
Limits of the construction permit
The permit authorizes construction only. Before fuel can be loaded or the reactors operated, the company must win a separate operating license, the NRC’s release says. The agency said the same thing when it docketed the application: “The construction permit, if approved, would not authorize the operation of the units.”
Dow is also careful about its own commitment. In its Nov. 9 press release, the company said the permit does not commit it to construct anything. Remaining steps include finalizing engineering and design and review by Dow’s board of directors. Edward Stones, the company’s business vice president for energy and climate, called the permit “another important milestone for the proposed Long Mott Generating Station project,” and said Dow will weigh competitiveness, execution readiness and capital affordability before any construction decision.
ANS reported that a preliminary investment decision is expected in 2027, with construction possibly starting later this decade and commercial operation in the early 2030s. No final investment decision has been made.
Federal money behind the project
The project sits inside the Department of Energy’s Advanced Reactor Demonstration Program, which ANS says has put up roughly $2.15 billion in cost-shared funding. In a Nov. 13 DOE article, Principal Deputy Assistant Secretary for Nuclear Energy Mike Goff said the milestone “marks a significant step forward for the Department of Energy’s Advanced Reactor Demonstration Program.” The same DOE article notes that X-energy’s fuel subsidiary, TRISO-X, finished vertical construction of its TX-1 fuel fabrication facility in Oak Ridge, Tennessee, in September. The permit, DOE said, lets Dow and X-energy move toward construction readiness, finalize the Xe-100 design, secure long-lead components and prepare an operating license application.
The open question is the one Dow’s board has yet to answer. A 2027 preliminary investment decision will show whether a chemical company is prepared to carry four first-of-a-kind reactors on its books.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- A dangerous flash flood warning hit Broward County after an overnight deluge
- El Niño has hit +2.5°C, and a strong-to-very-strong winter event now looks likely
- The biggest grid drop in PJM history came from data centers, and now they may have to pay
- Back-to-back California quakes, and what the USGS says about the risk of a bigger one