On a mesa south of Albuquerque, a $1 billion campus is going up around a machine that will one day burn a radioactive form of hydrogen. This month New Mexico gave the company building it, Pacific Fusion, a first-ever license to use that fuel, the isotope tritium.
Read next on Morning Overview: Apple quietly pushed security fixes to nearly every iPhone, even ones stuck on iOS 18
The New Mexico Environment Department (NMED) announced the approval on Nov. 20. It is the first radioactive materials license the state has issued to a private fusion company, and it sets a hard ceiling on how much tritium can sit on the site: 15,000 curies, roughly 1.5 grams.
What the NMED license lets Pacific Fusion hold
According to Pacific Fusion’s announcement, the license authorizes the company to possess and use tritium for fusion at its Research and Manufacturing Campus in Albuquerque. The company says the tritium stays in a closed system and that waste goes to a licensed facility outside New Mexico.
The numbers come from the trade press. Nuclear Newswire, published by the American Nuclear Society, reported that the license covers fabricating and testing deuterium-tritium fusion targets and running experiments, with the 15,000-curie cap. Pacific Fusion told the outlet it “never intends to have an inventory that exceeds 10,000 curies.” The Albuquerque Journal added that the company plans to buy its tritium from an unnamed commercial supplier rather than from national laboratories, a point spokesperson Joanie Griffin confirmed.
Tritium is a hydrogen isotope with a half-life of just over 12 years, the Journal noted, citing the U.S. Nuclear Regulatory Commission. The 1.5-gram ceiling sounds tiny, and the 10,000-curie working figure the company gave Nuclear Newswire is lower still, a margin Pacific Fusion says it will keep as construction continues in coordination with NMED.
Why a state agency, and not the NRC, signed off
Fusion machines are not reactors in the fission sense, and New Mexico regulates them the way it regulates other users of radioactive material. Per POWER magazine’s account of the announcement, NMED oversees fusion under a framework similar to the one used for hospitals and research facilities.
The federal layer sits behind that. Nuclear Newswire reported that the NRC has proposed folding fusion machines into the existing byproduct material framework, which leaves licensing to Agreement States such as New Mexico, and that an NRC letter from August found the state’s proposed fusion license conditions largely acceptable, asking that one comment be addressed in the final draft. The article did not say what that comment was.
The result is a state-issued document, reviewed against federal expectations, for a technology with no earlier license in the state to copy.
The pulser machine and the 2030 target
Pacific Fusion, headquartered in California and founded in 2023, is building a pulser-driven inertial fusion system from modular components, according to World Nuclear News. The same report places the campus at Mesa del Sol, says groundbreaking took place in August 2026, and says the planned Demonstration System is meant to reach net facility gain by 2030. Net facility gain is the point at which a fusion shot returns more energy than the facility spends producing it.
Carrie von Muench, the company’s co-founder and chief operating officer, called the license “an essential milestone” on the way to putting clean fusion energy on the grid, and said leaders across the state had shown what government and industry can do together. World Nuclear News also relayed the company’s description of the facility as the only “high-yield” fusion facility under construction in the United States, with bursts above 100 megajoules, a capability it said supports national security research. That description comes from the company side of the story, and the license itself says nothing about yield.
The company has also started making hardware. Pacific Fusion says it has hired 90 people at its Los Lunas Build Center, where modular pulser components are built, and expects the Albuquerque campus to create more than 200 permanent jobs plus hundreds of construction jobs. Nuclear Newswire also noted two recent U.S. Department of Energy INFUSE awards to the company, one to measure praseodymium cross sections for activation-based diagnostics and one to study a target class that needs no external coil to premagnetize it.
The state money behind the campus
New Mexico has put public money into the project well before the tritium license. The Albuquerque Journal reported that Pacific Fusion received $776.6 million in industrial revenue bonds last year, which carry tax exemptions for 20 years, along with $10 million in Local Economic Development Act funds committed by the state and the city of Albuquerque, and nearly $4 million through the state’s Job Training Incentive Program.
State Environment Secretary James Kenney tied the license to those goals. Quoted in the Journal, he said New Mexico is proving it can lead the clean energy transition while creating good-paying jobs, and that the state’s Energy Transition Act set ambitious goals for a zero-carbon electricity future. POWER magazine carried a shorter line from him, that innovations like fusion “could play an important role” in helping reach those goals.
The Journal’s piece carried no public comment or opposition, so how neighbors near Mesa del Sol view a tritium-handling campus is not yet on the record. The open question for the project is the one the 2030 target raises: whether the Demonstration System reaches net facility gain, which no license can decide.
This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.
More from Morning Overview
- Ukraine says a Flamingo missile helped drop a span of the Crimean Bridge into the sea
- A mayday over Florida: an American 737 shut down an engine and diverted to Orlando
- A dangerous flash flood warning hit Broward County after an overnight deluge
- The biggest grid drop in PJM history came from data centers, and now they may have to pay