Skip to main content

Morning Overview

Japan is pouring public money into a fusion machine called Helix HARUKA

At the National Institute for Fusion Science campus in Toki, Gifu Prefecture, one of the twisting three-dimensional coils for a new machine is close to finished. The machine is Helix HARUKA, and Japan’s government is now pouring public money into it: up to JPY 19.2 billion, about $126 million, awarded to the Tokyo company Helical Fusion.

Read next on Morning Overview: Washington is forcing coal plants from Colorado to Washington state to keep running

The subsidy comes from Japan’s Ministry of Economy, Trade and Industry (METI) and was disclosed in a company release dated Nov. 18. It is meant to carry the company from a half-built test device toward a design for its first power plant, and it runs through February 2029.

What the JPY 19.2 billion pays for

According to Helical Fusion’s announcement on Business Wire, the money is a maximum, not a guaranteed payout, and it covers three areas. The first is manufacturing and assembly of Helix HARUKA, which the company calls an Integrated Demonstration Device. The second is basic engineering design of Helix KANATA, the planned first fusion power plant. The third is development of critical components for commercial fusion.

Helical Fusion leads overall plant design and systems integration and works with about 40 Japanese companies, the release says, drawing on research from national institutions. With the subsidy included, the company counts about JPY 33.2 billion, or about $218 million, in cumulative funding and financing commitments.

The weekly digest The Fusion Report carried the same figures in its Nov. 20 issue, including the JPY 33.2 billion cumulative total and the 2027 coil-energization step.

Private money is moving alongside the public grant. The Business Wire page lists a second close of the company’s Series B round in October that raised about $20.6 million, or JPY 3.23 billion, with Fuji Electric joining as a strategic investor, and a July memorandum of understanding with the general contractor HAZAMA ANDO toward building a fusion pilot plant. Those items sit in the page’s related-news sidebar, so their detail comes from the company’s own summaries.

A stellarator instead of a tokamak

Helical Fusion builds a stellarator, a design that twists the plasma vessel itself instead of relying on the uniform doughnut shape of tokamaks such as ITER. World Nuclear News described the trade this way: the twisted geometry avoids the tokamak problem of confining coils being less dense on the outside of the ring. The company’s own requirements for a commercial plant are steady-state operation, net electricity and parts that can be maintained efficiently.

The company was founded in 2021 as a spin-out of the National Institute for Fusion Science, and its design leans on that institute’s Large Helical Device, which sustained plasma for 3,268 seconds, according to the Business Wire release. CEO Takaya Taguchi said in the release that the company chose the stellarator because it believes the design offers the strongest route to a reliable, commercially viable source of electricity, and that it intends to prove the case through measurable engineering progress.

The schedule for Helix HARUKA

The timeline is concrete only in its first step. Phase 1 includes energization testing of high-temperature superconducting (HTS) coils in 2027. Phase 2, in the early 2030s, tests integrated operation of those coils with blanket systems before a first plant is built. KANATA’s design work is set to proceed in parallel and not wait for every test to finish, and the company targets commercially viable fusion power in the 2030s.

A profile on Fusion Energy Base describes HARUKA as a testbed combining HTS magnets and a liquid-metal blanket, aiming for continuous runs of more than 24 hours and operation around 2030. That profile is a third-party summary; the company release gives only the 2027 and early-2030s phases.

How Helical Fusion got to the final award

The Nov. 18 announcement is described by the company as the grant award, and it followed a selection that began in the late summer. On Sept. 2, the Fusion Industry Association reported that METI had conditionally picked four industry-led projects for a fusion power demonstration program: EX-Fusion, with Hamamatsu Photonics, for laser fusion; Helical Fusion for a stellarator; LINEA Innovation for a beam-supported field-reversed configuration; and Starlight Engine, with Kyoto Fusioneering, for a superconducting tokamak.

The association put the pool at about JPY 60 billion in government support over three years, through 2028, paid on milestones, with individual allocations not yet set and finalization expected as early as October. World Nuclear News reported the same approximate total, about $370 million, through the end of February 2029.

Helical Fusion’s JPY 19.2 billion is the first individual figure from that pool that appears in the sources read for this article. The releases found do not say what METI awarded the other three projects, or whether the money has been finalized for them, so the share of the JPY 60 billion that Helical Fusion’s award represents cannot be stated from them.

This article was produced with the assistance of AI and reviewed by Morning Overview editors prior to publication.