NASA has confirmed a new target date for the second Artemis II wet dress rehearsal, setting Thursday, February 19, 2026, as tanking day for the Space Launch System rocket at Kennedy Space Center. The announcement follows weeks of troubleshooting after the first rehearsal was cut short by a liquid hydrogen leak, and it signals that engineers believe their fixes are ready for a full-duration test. With a March launch window narrowing, the outcome of this second attempt will determine whether the first crewed lunar mission since Apollo stays on schedule or slips further into spring.
February 19 Tanking Day and the 50-Hour Countdown
The nearly 50-hour countdown sequence is set to begin on February 17, building toward a simulated launch time of 8:30 p.m. on February 19, according to NASA’s mission update. That timeline mirrors the structure of the first rehearsal, which also ran roughly 49 hours before its simulated window. The rehearsal will load the SLS core stage and upper stage with cryogenic propellant, walk through terminal countdown procedures, and then drain the tanks to practice scrub turnaround operations. A full Moon was visible over the SLS and Orion spacecraft atop the mobile launcher at Kennedy Space Center on the night of the announcement, a fitting backdrop for a mission designed to send four astronauts around the Moon.
The scale of the operation is significant. The wet dress rehearsal involves pumping over 700,000 gallons of cryogenic propellant into the rocket, as NASA previously detailed for the first attempt. Every valve, seal, and ground support connection must perform under extreme cold, and the full countdown gives launch controllers a chance to rehearse real-time decision-making under flight-like conditions. The first rehearsal was originally targeted for as early as January 31, which means the program has now absorbed roughly three weeks of schedule margin working through hardware issues. With the second rehearsal now locked in, teams are treating the February 19 tanking as a dress rehearsal not just for fueling, but for the entire launch-day choreography.
What Went Wrong in the First Rehearsal
The first wet dress rehearsal ran into trouble well before reaching its simulated liftoff. During the countdown, a valve inadvertently vented during seal pressurization checks, requiring controllers to halt and conduct re-pressurization work before moving forward. The test entered a T-10 minute hold at 8:50 p.m. EST while teams assessed the situation and verified that the anomaly had not damaged hardware. After resuming, the countdown appeared to be back on track, but the more consequential problem emerged later, when sensors detected abnormal hydrogen concentrations near the base of the rocket.
As controllers narrowed in on the source, they determined that a liquid hydrogen leak had developed at the tail service mast umbilical interface, the critical connection point where ground equipment feeds super-cold fuel into the rocket’s core stage. The countdown was ultimately terminated at T‑5:15, just minutes before the planned simulated liftoff time. NASA described a methodical sequence to safe the vehicle and drain the tanks after the termination, prioritizing hardware protection and personnel safety. While the scrub was a setback, the incident also provided a trove of data about how the ground systems and the rocket behave under full cryogenic loading.
From Leak to Confidence Test
The leak discovery was not a total loss. Cryogenic propellant loading and a safe drain were both achieved during the first attempt, and closeout operations were completed, according to NASA’s post-test summary. That means the ground systems and the rocket demonstrated they could handle the thermal shock of loading and offloading liquid hydrogen and liquid oxygen, even if the countdown itself could not reach its final minutes. NASA followed the test with a news conference featuring senior leaders and the Artemis launch team to walk through initial findings, emphasizing that the primary issue was localized to the umbilical connection rather than a systemic flaw in the SLS core stage.
In the days that followed, technicians accessed the tail service mast umbilical area, inspected the suspect seals, and began planning a path toward a targeted re-test. The strategy was to replace the seals at the interface, then design a smaller-scale fueling run to validate the fix before committing to another full 50-hour rehearsal. That approach culminated in a February 12 confidence test, which partially filled the SLS core stage liquid hydrogen tank to evaluate the new seals under realistic thermal conditions. By proceeding in stages (first a focused confidence run, then a full countdown), NASA aimed to reduce the risk of repeating the same failure mode during the second wet dress rehearsal.
The Confidence Test and a Stubborn Filter
During the February 12 run, engineers monitored the newly installed seals at the umbilical interface where the earlier leak had occurred. According to NASA’s data review update, the seals appeared to perform as intended, with no recurrence of the hydrogen leak that ended the first rehearsal. However, the test surfaced a different concern: ground support equipment unexpectedly reduced the flow of liquid hydrogen during the core stage fill. Teams traced the flow restriction to a suspected filter in the ground plumbing and outlined plans to inspect, clean, or replace the component before attempting a full-duration countdown.
This kind of iterative fix-and-retest cycle is standard for programs of this complexity, but it also highlights a tension that rarely gets enough attention in Artemis coverage. Much of the public discussion focuses on the SLS rocket and Orion capsule as flight hardware, yet ground support equipment failures have been a recurring source of delays across the Artemis program. The tail service mast, the mobile launcher’s umbilical connections, and the propellant delivery lines at Launch Complex 39B are all one-of-a-kind systems that cannot be fully validated until they interact with a flight vehicle loaded with cryogenic fluids. The February 12 confidence test is a case study: the flight hardware seals held, but a ground-side filter choked the flow. If the second wet dress rehearsal succeeds on February 19, it will be as much a validation of the launch pad infrastructure as it is of the rocket itself.
March Launch Windows Under Pressure
The stakes of the February 19 rehearsal extend well beyond the test itself. NASA has stated it will target March 2026 as the earliest possible launch opportunity for Artemis II, contingent on completing data review and a successful second wet dress rehearsal. Earlier in the campaign, the agency outlined a series of late-winter launch opportunities that depend on lighting, communications, and trajectory constraints for the mission’s lunar flyby profile. Each delay in the fueling tests chips away at that margin, increasing the likelihood that the first crewed Artemis flight could be pushed into a later spring window if additional issues emerge.
NASA’s broader planning underscores why managers are intent on resolving ground issues now rather than accepting elevated risk later. Agency leaders have framed Artemis II as a crucial stepping stone in the Moon to Mars exploration strategy, with the mission designed to test life support, navigation, and deep-space operations for the Orion spacecraft before attempting a lunar landing on Artemis III. In a recent overview of the mission’s remaining work, NASA described final steps underway for crew training, spacecraft integration, and systems verification. All of those efforts ultimately hinge on the SLS and its ground systems proving they can fuel, count down, and recycle under real-world conditions, exactly what the February 19 wet dress rehearsal is intended to demonstrate.